Found 127 Results

2010 – I-15 / Pioneer Crossing Bridge

State: UT
Year: 2010
Owner: State
Location: Urban
Beam material: Concrete

Spans: One-span
Max Span Length (ft.): 191
Total Bridge Length (ft.): 191
Impact Category: Tier 1 (within 1 day)
Construction Equipment Category: SPMTs

Project Planning: State process, design-build, alternative technical concept, full lane closure, incentive / disincentive clause
Geotechnical Solutions: embankment surcharge
Structural Solutions: MSE wall, FDcBc (full-width concrete-decked concrete beam unit), CIP reinforced closure joint


2010 – US 17 Bridge over Tar River (Washington Bypass)

State: NC
Year: 2010
Owner: State
Location: Rural
Beam material: Concrete

Spans: > Three-span
Max Span Length (ft.): 121.67
Total Bridge Length (ft.): 14784
Impact Category: Tier 6 (longer but reduced by months/years)
Construction Equipment Category: Other ABC Method

Project Planning: design-build, full lane closure, incentive / disincentive clause, formalized partnering
Geotechnical Solutions:
Structural Solutions: precast pile cap, PT ducts/bonded, socket connection (in precast substructure)


2009 – 640th Street Bridge over Branch Raccoon River

State: IA
Year: 2009
Owner: County
Location: Rural
Beam material: Concrete

Spans: One-span
Max Span Length (ft.): 50.83
Total Bridge Length (ft.): 50.83
Impact Category: Tier 3 (within 2 weeks)
Construction Equipment Category: Conventional

Project Planning: design-bid-build, full lane closure, incentive / disincentive clause
Geotechnical Solutions:
Structural Solutions: adjacent box beam, precast abutment cap, precast backwall, precast wingwall, grouted key closure joint, socket connection (in precast substructure), epoxy joint


2009 – Route 31 Bridge over Canandaigua Outlet

State: NY
Year: 2009
Owner: State
Location: Rural
Beam material: Concrete

Spans: One-span
Max Span Length (ft.): 87.42
Total Bridge Length (ft.): 87.42
Impact Category: Tier 5 (within 3 months)
Construction Equipment Category: Conventional

Project Planning: Design-bid-build,
Geotechnical Solutions:
Structural Solutions: Adjacent deck bulb T beams, CIP reinforced closure joints, UHPC closure joints, asphalt overlay w/membrane


2009 – Black Cat Road Bridge

State: ID
Year: 2009
Owner: State
Location: Urban
Beam material: Concrete

Spans: Two-span
Max Span Length (ft.): 97
Total Bridge Length (ft.): 196
Impact Category: Tier 6 (longer but reduced by months/years)
Construction Equipment Category: Conventional

Project Planning: design-bid-build, full lane closure, incentive / disincentive clause
Geotechnical Solutions:
Structural Solutions: precast cap & column(s), MSE wall, bars in splice coupler, grouted duct connection (in precast substructure)


2009 – MD 362 Bridge over Monie Creek

State: MD
Year: 2009
Owner: State
Location: Rural
Beam material: Concrete

Spans: One-span
Max Span Length (ft.): 55
Total Bridge Length (ft.): 55
Impact Category: Tier 5 (within 3 months)
Construction Equipment Category: Conventional

Project Planning: design-bid-build, full lane closure, incentive / disincentive clause
Geotechnical Solutions:
Structural Solutions: adjacent slab beam, precast abutment cap, precast wingwall, steel sheet piling, CIP reinforced closure joint, grouted key closure joint, bars in splice coupler, PT ducts/bonded, socket connection (in precast substructure)-(caps), precast curb, latex-modified overlay


2009 – Route 23 Bridge over Otego Creek

State: NY
Year: 2009
Owner: State
Location: Rural
Beam material: Steel

Spans: One-span
Max Span Length (ft.): 131.2
Total Bridge Length (ft.): 131.2
Impact Category: Tier 5 (within 3 months)
Construction Equipment Category: Conventional

Project Planning: Design-bid-build,
Geotechnical Solutions:
Structural Solutions: Full-depth precast deck panel w/o PT (with UHPC closure joints), CIP reinforced closure joints, UHPC closure joints, standard concrete overlay


2009 – CTH B Bridge over Parsons Creek

State: WI
Year: 2009
Owner: Fond du Lac County
Location: Rural
Beam material: Concrete

Spans: One-span
Max Span Length (ft.): 21.67
Total Bridge Length (ft.): 21.67
Impact Category: Tier 5 (within 3 months)
Construction Equipment Category: Conventional

Project Planning: In-house force: county crews, Full lane closure
Geotechnical Solutions:
Structural Solutions: Precast 3-sided culvert; Precast wingwalls, Grouted key closure joints


2009 – I-80 Bridge over 2300 East

State: UT
Year: 2009
Owner: State
Location: Urban
Beam material: Concrete

Spans: One-span
Max Span Length (ft.): 80
Total Bridge Length (ft.): 80
Impact Category: Tier 2 (within 3 days)
Construction Equipment Category: Lateral Slide

Project Planning: State process, design-build (low bid), full lane closure; incentive / disincentive clause
Geotechnical Solutions:
Structural Solutions: FDcBc (full-width concrete-decked concrete beam unit), precast approach slab; LWC deck


2009 – Inyan Kara Creek Bridge

State: WY
Year: 2009
Owner: Crook County
Location: Rural
Beam material: Concrete

Spans: One-span
Max Span Length (ft.): 85
Total Bridge Length (ft.): 85
Impact Category: Tier 5 (within 3 months)
Construction Equipment Category: Conventional

Project Planning: design-bid-build, full lane closure
Geotechnical Solutions:
Structural Solutions: adjacent deck bulb T beam, precast abutment cap, precast backwall, precast wingwall, grouted key closure joint