![](https://utcdb.fiu.edu/wp-content/uploads/2021/09/P1-MA-Phillipston-2346-scaled-1.jpg)
2010 – Phillipston Bridge
State: MA
Year: 2010
Owner: State
Location: Urban
Beam material: Steel
Spans: One-span
Max Span Length (ft.): 60.67
Total Bridge Length (ft.): 60.67
Impact Category: Tier 3 (within 2 weeks)
Construction Equipment Category: SPMTs
Project Planning: State process,
Design-Build,
Full lane closure; Incentive / disincentive clauses; No Excuse bonus; Lump Sum bonus
Geotechnical Solutions:
Structural Solutions: Precast abutment cap w/backwall,
FDcBs (Full-width decked beam),
Asphalt overlay w/membrane
![](https://utcdb.fiu.edu/wp-content/uploads/2021/09/P1-UT-Layton-05_shows-surcharge-and-girders-at-temp-location-scaled-1.jpg)
2010 – I-15 / Layton Parkway Bridge
State: UT
Year: 2010
Owner: State
Location: Urban
Beam material: Steel
Spans: Two-span
Max Span Length (ft.): 108.8
Total Bridge Length (ft.): 217.8
Impact Category: Tier 1 (within 1 day)
Construction Equipment Category: Longitudinal Launching
Project Planning: State process,
design-build,
incentive / disincentive clauses
Geotechnical Solutions: embankment surcharge
Structural Solutions: MSE walls,
FDcBs (full-width concrete-decked steel beam unit),
CIP reinforced concrete closure joints, thin-bonded epoxy overlay, LWC deck
![](https://utcdb.fiu.edu/wp-content/uploads/2021/09/P1-NC-Biltmore-DSC03581-scaled-1.jpg)
2010 – Biltmore Avenue Bridge
State: NC
Year: 2010
Owner: State
Location: Urban
Beam material: Steel
Spans: One-span
Max Span Length (ft.): 135
Total Bridge Length (ft.): 135
Impact Category: Tier 6 (longer but reduced by months/years)
Construction Equipment Category: Conventional
Project Planning: • Design-Bid-Build,
• Full lane closure
Geotechnical Solutions: • Micropiles,
Structural Solutions: MDcBs (Modular decked beams),
CIP reinforced concrete closure joints
![](https://utcdb.fiu.edu/wp-content/uploads/2021/09/P3-Pioneer-Aspire-Winter-2011-3-scaled.jpg)
2010 – I-15 / Pioneer Crossing Bridge
State: UT
Year: 2010
Owner: State
Location: Urban
Beam material: Concrete
Spans: One-span
Max Span Length (ft.): 191
Total Bridge Length (ft.): 191
Impact Category: Tier 1 (within 1 day)
Construction Equipment Category: SPMTs
Project Planning: State process,
Design-build; Alternative Technical Concept,
Full lane closure; Incentive / disincentive clauses
Geotechnical Solutions: Embankment surcharge
Structural Solutions: MSE walls,
FDcBc (full-width concrete-decked concrete beam unit),
CIP reinforced concrete closure joints
![](https://utcdb.fiu.edu/wp-content/uploads/2021/09/PA7-NC-US17_391-2012-PCI-NBC.jpg)
2010 – US 17 Bridge over Tar River (Washington Bypass)
State: NC
Year: 2010
Owner: State
Location: Rural
Beam material: Concrete
Spans: > Three-span
Max Span Length (ft.): 121.67
Total Bridge Length (ft.): 14784
Impact Category: Tier 6 (longer but reduced by months/years)
Construction Equipment Category: Other ABC Method
Project Planning: Design-build,
Full lane closure; Incentive / disincentive clauses; Formalized partnering
Geotechnical Solutions:
Structural Solutions: Precast pile caps,
PT ducts/bonded; Socket connection (in precast substructure)
![](https://utcdb.fiu.edu/wp-content/uploads/2021/09/P1-NH-I93Loudon-100_2241-scaled-1.jpg)
2010 – I-93 Bridge over Loudon Road (Route 9)
State: NH
Year: 2010
Owner: State
Location: Urban
Beam material: Steel
Spans: One-span
Max Span Length (ft.): 82
Total Bridge Length (ft.): 82
Impact Category: Tier 2 (within 3 days)
Construction Equipment Category: Conventional
Project Planning: State Process,
Design-bid-build,
Incentive / disincentive clauses; No Excuse bonus; Value Engineering
Geotechnical Solutions:
Structural Solutions: Full-depth precast deck panel w/PT,
CIP reinforced concrete closure joints; Grouted key closure joints; PT ducts/bonded; Asphalt overlay w/membrane
![](https://utcdb.fiu.edu/wp-content/uploads/2021/09/P1-ID-VistaIC-P1010001.jpg)
2010 – Vista Interchange Bridge
State: ID
Year: 2010
Owner: State
Location: Urban
Beam material: Concrete
Spans: Two-span
Max Span Length (ft.): 91.5
Total Bridge Length (ft.): 182
Impact Category: Tier 6 (longer but reduced by months/years)
Construction Equipment Category: Conventional
Project Planning: Design-bid-build,
Lane rental; Value Engineering
Geotechnical Solutions:
Structural Solutions: Precast column cap (precast bent cap; precast crossbeam); Precast abutment cap; MSE wall,
Bars in splice couplers; Grouted duct connection (in precast substructure)
![](https://utcdb.fiu.edu/wp-content/uploads/2021/09/P2-DC-Eastern-Avenue.jpg)
2010 – Eastern Avenue Bridge
State: DC: District of Columbia
Year: 2010
Owner: District Department of Transportation
Location: Urban
Beam material: Concrete
Spans: Two-span
Max Span Length (ft.): 42.33
Total Bridge Length (ft.): 84.67
Impact Category: Tier 6 (longer but reduced by months/years)
Construction Equipment Category: Conventional
Project Planning: Design-bid-build,
Full lane closure
Geotechnical Solutions: Other foundation/wall: undercut unsuitable in-situ materials and replaced with compacted aggregate base under spread footing,
Structural Solutions: MDcBs (Modular decked beams); Precast cap & column(s),
CIP reinforced concrete closure joints; Grouted key closure joints; Asphalt overlay w/membrane; LWC deck
![](https://utcdb.fiu.edu/wp-content/uploads/2021/09/P2-NJ-GordonsCornerRd_erection-2.jpg)
2010 – Gordon’s Corner Road Bridge over Route 9
State: NJ
Year: 2010
Owner: State
Location: Urban
Beam material: Steel
Spans: Two-span
Max Span Length (ft.): 59
Total Bridge Length (ft.): 118
Impact Category: Tier 2 (within 3 days)
Construction Equipment Category: Conventional
Project Planning:
• Design-bid-build
,• Full lane closure• Incentive / disincentive clauses
Geotechnical Solutions:
Structural Solutions:
• Modular decked beams (MDcBs)
, CIP reinforced concrete closure joints; Precast approach slabs![](https://utcdb.fiu.edu/wp-content/uploads/2021/09/P1-SC-BenSawyer.jpg)
2010 – Ben Sawyer Swing Bridge
State: SC
Year: 2010
Owner: State
Location: Urban
Beam material: Steel
Spans: > Three-span
Max Span Length (ft.): 247
Total Bridge Length (ft.): 1154
Impact Category: Tier 3 (within 2 weeks)
Construction Equipment Category: Lateral Slide
Project Planning: Design-build,
Full lane closure; Incentive / disincentive clauses
Geotechnical Solutions: Reused substructure/foundation unit,
Structural Solutions: Exodermic deck,
Truss span w/deck; FDcBs (full-width concrete-decked steel beam unit),
LWC deck