2008 – Riverdale Road Bridge over I-84
State: UT
Year: 2008
Owner: State
Location: Urban
Beam material: Steel
Spans: Two-span
Max Span Length (ft.): 76.5
Total Bridge Length (ft.): 155.5
Impact Category: Tier 1 (within 1 day)
Construction Equipment Category: Conventional
Project Planning: State process,
CM/GC,
full lane closure, incentive / disincentive clause
Geotechnical Solutions: lightweight fill
Structural Solutions: full-depth precast deck panel w/PT, precast cap & column(s), precast abutment stem, MSE wall,
CIP reinforced closure joint, grouted key closure joint, PT ducts/bonded, match cast closure joint, epoxy joint, polymer concrete overlay, precast approach slab, precast diaphragm

2008 – NC 12 Bridge over Molasses Creek
State: NC
Year: 2008
Owner: State
Location: Urban
Beam material: Concrete
Spans: > Three-span
Max Span Length (ft.): 51
Total Bridge Length (ft.): 252
Impact Category: Tier 5 (within 3 months)
Construction Equipment Category: Conventional
Project Planning: design-bid-build,
full lane closure, incentive / disincentive clause, lump sum bonus, contractor revision
Geotechnical Solutions:
Structural Solutions: adjacent slab beam, precast pile cap, precast abutment cap, precast backwall, precast wingwall, precast abutment footing,
grouted key closure joint, PT ducts/un-bonded, socket connection (in precast caps), grouted duct connection (in precast backwalls), asphalt overlay w/o membrane, prefabricated railing

2008 – 24th Street Bridge over I-29/I-80
State: IA
Year: 2008
Owner: State
Location: Urban
Beam material: Steel
Spans: Two-span
Max Span Length (ft.): 178.5
Total Bridge Length (ft.): 353.5
Impact Category: Tier 6 (longer but reduced by months/years)
Construction Equipment Category: Conventional
Project Planning: design-bid-build,
A+B bidding, incentive / disincentive clause
Geotechnical Solutions: fully-contained flooded backfill
Structural Solutions: full-depth precast deck panel w/PT,
CIP reinforced closure joint, grouted key closure joint, grouted blockout w/shear connector, PT ducts/bonded, standard concrete overlay

2008 – Jakway Park Bridge
State: IA
Year: 2008
Owner: County
Location: Rural
Beam material: Concrete
Spans: Three-span
Max Span Length (ft.): 51.17
Total Bridge Length (ft.): 115.33
Impact Category: Tier 5 (within 3 months)
Construction Equipment Category: Conventional
Project Planning: design-bid-build,
full lane closure
Geotechnical Solutions:
Structural Solutions: other deck beam element: pi-girder,
steel diaphragm, CIP reinforced closure joint, grouted key closure joint, asphalt chip seal w/o membrane

2008 – Elk Creek Bridge (Crossing No. 3)
State: OR
Year: 2008
Owner: State
Location: Rural
Beam material: Steel
Spans: Three-span
Max Span Length (ft.): 207.5
Total Bridge Length (ft.): 320.5
Impact Category: Tier 2 (within 3 days)
Construction Equipment Category: Lateral Slide
Project Planning: State process,
early environmental clearance & permitting,
design-build,
full lane closure, incentive / disincentive clause
Geotechnical Solutions: CIP substructure under traffic,
Structural Solutions: precast wingwall,
FDcBs (full-width concrete-decked steel beam unit),
CIP reinforced closure joint, precast approach slab, other miscellaneous prefabricated element – precast sleeper slab

2008 – Hardscrabble Creek Bridge
State: CA
Year: 2008
Owner: State
Location: Rural
Beam material: Concrete
Spans: One-span
Max Span Length (ft.): 133.5
Total Bridge Length (ft.): 133.5
Impact Category: Tier 1 (within 1 day)
Construction Equipment Category: Lateral Slide
Project Planning: Design-bid-build,
Full lane closure
Geotechnical Solutions:
Structural Solutions: Prestressed multi-cell box girder span,

2008 – MD 28 Bridge over Washington Run
State: MD
Year: 2008
Owner: State
Location: Rural
Beam material: Concrete
Spans: One-span
Max Span Length (ft.): 40
Total Bridge Length (ft.): 40
Impact Category: Tier 5 (within 3 months)
Construction Equipment Category: Conventional
Project Planning: design-bid-build,
full lane closure, incentive / disincentive clause
Geotechnical Solutions:
Structural Solutions: adjacent slab beam,
grouted key closure joint, PT ducts/bonded, standard concrete overlay

2008 – Kimberly Bridge
State: OR
Year: 2008
Owner: State
Location: Rural
Beam material: Concrete
Spans: One-span
Max Span Length (ft.): 42
Total Bridge Length (ft.): 42
Impact Category: Tier 3 (within 2 weeks)
Construction Equipment Category: Conventional
Project Planning: State process,
design-bid-build,
full lane closure
Geotechnical Solutions:
Structural Solutions: adjacent slab beam, precast abutment cap,
grouted key closure joint, socket connection (in precast substructure), asphalt overlay w/membrane (Spans 1 & 5 only), precast curb

2008 – MD 450 Bridge over Bacon Ridge Branch
State: MD
Year: 2008
Owner: State
Location: Rural
Beam material: Concrete
Spans: One-span
Max Span Length (ft.): 58
Total Bridge Length (ft.): 58
Impact Category: Tier 5 (within 3 months)
Construction Equipment Category: Conventional
Project Planning: design-bid-build,
full lane closure, incentive / disincentive clause
Geotechnical Solutions:
Structural Solutions: adjacent slab beam,
grouted key closure joint, PT ducts/bonded, standard concrete overlay

2008 – Route 70 Bridge over Manasquan River (September 11 Memorial Bridge)
State: NJ
Year: 2008
Owner: State
Location: Urban
Beam material: Concrete
Spans: > Three-span
Max Span Length (ft.): 120.25
Total Bridge Length (ft.): 724
Impact Category: Tier 6 (longer but reduced by months/years)
Construction Equipment Category: Other ABC Method
Project Planning: right-of-way acquisition,
design-bid-build,
lane rental, incentive / disincentive clause
Geotechnical Solutions:
Structural Solutions: precast caisson cap, precast cap & column(s), MSE wall,
PT ducts/bonded, prefabricated railing, steel diaphragm, other miscellaneous element – noise wall panel and post