Reset Search

2008 – Riverdale Road Bridge over I-84
State: UT
Year: 2008
Owner: State
Location: Urban
Beam material: Steel
Spans: Two-span
Max Span Length (ft.): 76.5
Total Bridge Length (ft.): 155.5
Impact Category: Tier 1 (within 1 day)
Construction Equipment Category: Conventional
Project Planning: State process,
CM/GC,
Full lane closure; Incentive / disincentive clauses
Geotechnical Solutions: Lightweight fill
Structural Solutions: Full-depth precast deck panel w/PT; Precast cap & column(s); Precast abutment stems; MSE wall,
CIP reinforced concrete closure joint; Grouted key closure joint; PT ducts/bonded; Match cast closure joint; Epoxy joint; Polymer concrete overlay; Precast approach slab; Precast diaphragm

2008 – NC 12 Bridge over Molasses Creek
State: NC
Year: 2008
Owner: State
Location: Urban
Beam material: Concrete
Spans: > Three-span
Max Span Length (ft.): 51
Total Bridge Length (ft.): 252
Impact Category: Tier 5 (within 3 months)
Construction Equipment Category: Conventional
Project Planning: Design-bid-build,
Full lane closure; Incentive / disincentive clauses; Lump sum bonus; Contractor revision
Geotechnical Solutions:
Structural Solutions: Adjacent slab beams; Precast pile caps; Precast abutment caps; Precast backwalls; Precast wingwalls; Precast abutment footing,
Grouted key closure joint; PT ducts/un-bonded; Socket connection (in precast caps); Grouted duct connection (in precast backwalls); Asphalt overlay w/o membrane; Prefabricated railing

2008 – 24th Street Bridge over I-29/I-80
State: IA
Year: 2008
Owner: State
Location: Urban
Beam material: Steel
Spans: Two-span
Max Span Length (ft.): 178.5
Total Bridge Length (ft.): 353.5
Impact Category: Tier 6 (longer but reduced by months/years)
Construction Equipment Category: Conventional
Project Planning: Design-bid-build,
A+B bidding; Incentive / disincentive clauses
Geotechnical Solutions: Fully-contained flooded backfill
Structural Solutions: Full-depth precast deck panel w/PT,
CIP reinforced concrete closure joints; Grouted key closure joints; Grouted blockout w/shear connectors; PT ducts/bonded; Standard concrete overlay

2008 – Jakway Park Bridge
State: IA
Year: 2008
Owner: Buchanan County
Location: Rural
Beam material: Concrete
Spans: Three-span
Max Span Length (ft.): 51.17
Total Bridge Length (ft.): 115.33
Impact Category: Tier 5 (within 3 months)
Construction Equipment Category: Conventional
Project Planning: Design-bid-build,
Full lane closure
Geotechnical Solutions:
Structural Solutions: Other deck beam element: pi-girders,
CIP reinforced concrete closure joints; Grouted key closure joints; Asphalt chip seal w/o membrane; Steel diaphragms

2008 – Elk Creek Bridge (Crossing No. 3)
State: OR
Year: 2008
Owner: State
Location: Rural
Beam material: Steel
Spans: Three-span
Max Span Length (ft.): 207.5
Total Bridge Length (ft.): 320.5
Impact Category: Tier 2 (within 3 days)
Construction Equipment Category: Lateral Slide
Project Planning: State process,
Early environmental clearance & permitting,
Design-build,
Full lane closure; Incentive / disincentive clauses
Geotechnical Solutions: CIP substructure under traffic,
Structural Solutions: Precast wingwalls,
FDcBs (full-width concrete-decked steel beam unit),
CIP reinforced concrete closure joints; Precast approach slabs; Other miscellaneous element – sleeper slabs

2008 – Hardscrabble Creek Bridge
State: CA
Year: 2008
Owner: State
Location: Rural
Beam material: Concrete
Spans: One-span
Max Span Length (ft.): 133.5
Total Bridge Length (ft.): 133.5
Impact Category: Tier 1 (within 1 day)
Construction Equipment Category: Lateral Slide
Project Planning: Design-bid-build,
Full lane closure
Geotechnical Solutions:
Structural Solutions: Prestressed multi-cell box girder span,

2008 – MD 28 Bridge over Washington Run
State: MD
Year: 2008
Owner: State
Location: Rural
Beam material: Concrete
Spans: One-span
Max Span Length (ft.): 40
Total Bridge Length (ft.): 40
Impact Category: Tier 5 (within 3 months)
Construction Equipment Category: Conventional
Project Planning: Design-bid-build,
Full lane closure; Incentive / disincentive clauses
Geotechnical Solutions:
Structural Solutions: Adjacent slab beams,
Grouted key closure joints; PT ducts/bonded; Standard concrete overlay

2008 – Kimberly Bridge
State: OR
Year: 2008
Owner: State
Location: Rural
Beam material: Concrete
Spans: One-span
Max Span Length (ft.): 42
Total Bridge Length (ft.): 42
Impact Category: Tier 3 (within 2 weeks)
Construction Equipment Category: Conventional
Project Planning: State process,
Design-bid-build,
Full lane closure
Geotechnical Solutions:
Structural Solutions: Adjacent slab beams; Precast abutment caps,
Grouted key closure joints; Socket connection (in precast substructure); Asphalt overlay w/membrane (Spans 1 & 5 only); Precast curbs

2008 – MD 450 Bridge over Bacon Ridge Branch
State: MD
Year: 2008
Owner: State
Location: Rural
Beam material: Concrete
Spans: One-span
Max Span Length (ft.): 58
Total Bridge Length (ft.): 58
Impact Category: Tier 5 (within 3 months)
Construction Equipment Category: Conventional
Project Planning: Design-bid-build,
Full lane closure; Incentive / disincentive clauses
Geotechnical Solutions:
Structural Solutions: Adjacent slab beams,
Grouted key closure joints; PT ducts/bonded; Standard concrete overlay

2008 – Route 70 Bridge over Manasquan River (September 11 Memorial Bridge)
State: NJ
Year: 2008
Owner: State
Location: Urban
Beam material: Concrete
Spans: > Three-span
Max Span Length (ft.): 120.25
Total Bridge Length (ft.): 724
Impact Category: Tier 6 (longer but reduced by months/years)
Construction Equipment Category: Other ABC Method
Project Planning: Right-of-way acquisition,
Design-bid-build,
Lane rental; Incentive / disincentive clauses
Geotechnical Solutions:
Structural Solutions: Precast caisson caps; Precast cap & column(s); MSE walls,
PT ducts/bonded; Prefabricated railing; Steel diaphragms; Other miscellaneous element – noise wall panels and posts