2008 – 24th Street Bridge over I-29/I-80
State: IA
Year: 2008
Owner: State
Location: Urban
Beam material: Steel
Spans: Two-span
Max Span Length (ft.): 178.5
Total Bridge Length (ft.): 353.5
Impact Category: Tier 6 (longer but reduced by months/years)
Construction Equipment Category: Conventional
Project Planning: design-bid-build,
A+B bidding, incentive / disincentive clause
Geotechnical Solutions: fully-contained flooded backfill
Structural Solutions: full-depth precast deck panel w/PT,
CIP reinforced closure joint, grouted key closure joint, grouted blockout w/shear connector, PT ducts/bonded, standard concrete overlay

2008 – Jakway Park Bridge
State: IA
Year: 2008
Owner: County
Location: Rural
Beam material: Concrete
Spans: Three-span
Max Span Length (ft.): 51.17
Total Bridge Length (ft.): 115.33
Impact Category: Tier 5 (within 3 months)
Construction Equipment Category: Conventional
Project Planning: design-bid-build,
full lane closure
Geotechnical Solutions:
Structural Solutions: other deck beam element: pi-girder,
steel diaphragm, CIP reinforced closure joint, grouted key closure joint, asphalt chip seal w/o membrane

2008 – Elk Creek Bridge (Crossing No. 3)
State: OR
Year: 2008
Owner: State
Location: Rural
Beam material: Steel
Spans: Three-span
Max Span Length (ft.): 207.5
Total Bridge Length (ft.): 320.5
Impact Category: Tier 2 (within 3 days)
Construction Equipment Category: Lateral Slide
Project Planning: State process,
early environmental clearance & permitting,
design-build,
full lane closure, incentive / disincentive clause
Geotechnical Solutions: CIP substructure under traffic,
Structural Solutions: precast wingwall,
FDcBs (full-width concrete-decked steel beam unit),
CIP reinforced closure joint, precast approach slab, other miscellaneous prefabricated element – precast sleeper slab

2007 – SR 520 / SR 202 Interchange
State: WA
Year: 2007
Owner: State
Location: Urban
Beam material: Concrete
Spans: Three-span
Max Span Length (ft.): 145
Total Bridge Length (ft.): 435
Impact Category: Tier 5 (within 3 months)
Construction Equipment Category: Other ABC Method
Project Planning: Design-Bid-Build,
Contractor option
Geotechnical Solutions:
Structural Solutions: Precast column cap (precast bent cap; precast crossbeam); grouted duct connection,

2007 – Route 4 Bridge 50 over Ottauquechee River (Woodstock)
State: VT
Year: 2007
Owner: Town of Woodstock
Location: Urban
Beam material: Concrete
Spans: Three-span
Max Span Length (ft.): 84
Total Bridge Length (ft.): 202.5
Impact Category: Tier 4 (within 1 month)
Construction Equipment Category: Conventional
Project Planning: Other decision-making tool: Stakeholder Meetings held to present alternatives,
Right-of-Way acquisition,
Design-bid-build,
Full lane closure; Incentive / disincentive clause; Lump sum bonus; Value Engineering
Geotechnical Solutions: CIP substructure under traffic,
Structural Solutions: Adjacent box beams, Modular block walls,
CIP reinforced concrete closure joint; Grouted key closure joint; Asphalt overlay w/membrane; LWC beams

2007 – Martin Branch Bridge
State: TX
Year: 2007
Owner: Wise County
Location: Rural
Beam material: Steel
Spans: Three-span
Max Span Length (ft.): 50
Total Bridge Length (ft.): 150
Impact Category: Tier 6 (longer but reduced by months/years)
Construction Equipment Category: Conventional
Project Planning: Other Decision-Making Tool,
Programmatic Agreement,
Design-bid-build,
Full lane closure
Geotechnical Solutions:
Structural Solutions: Orthotropic deck - SPS (Sandwich Plate System); MDhBs (Modular hybrid-Decked steel Beam),
Polymer concrete overlay; Texas Type T6 railing

2007 – I-10 Bridge over Escambia Bay (Replacement Spans)
State: FL
Year: 2007
Owner: State
Location: Rural
Beam material: Concrete
Spans: > Three-span
Max Span Length (ft.): 250
Total Bridge Length (ft.): 13728
Impact Category: Tier 6 (longer but reduced by months/years)
Construction Equipment Category: Other ABC Method
Project Planning: early environmental clearance & permitting,
design-build,
A+B bidding, warranty, lane rental, incentive / disincentive clause
Geotechnical Solutions:
Structural Solutions: precast pile cap, precast footing(s),
pocket connection (in precast substructure)

2007 – I-215 / 4500 South Bridge
State: UT
Year: 2007
Owner: State
Location: Urban
Beam material: Concrete
Spans: One-span
Max Span Length (ft.): 172
Total Bridge Length (ft.): 172
Impact Category: Tier 2 (within 3 days)
Construction Equipment Category: SPMTs
Project Planning: State process,
CM/GC,
full lane closure
Geotechnical Solutions: CIP substructure under traffic,
self-compacting backfill
Structural Solutions: FDcBs (full-width concrete-decked steel beam unit),
precast approach slab, LWC deck

2007 – Parker River Bridge
State: MA
Year: 2007
Owner: U.S. Fish and Wildlife Service
Location: Urban
Beam material: Concrete
Spans: Three-span
Max Span Length (ft.): 30
Total Bridge Length (ft.): 90
Impact Category: Tier 6 (longer but reduced by months/years)
Construction Equipment Category: Conventional
Project Planning: Design-bid-build,
Geotechnical Solutions:
Structural Solutions: Adjacent slab beams; Precast pile caps; Precast abutment stems; Precast wingwalls,
Grouted key closure joints; PT ducts/un-bonded; Socket connection (in precast substructure)

2007 – Madison County Bridge
State: IA
Year: 2007
Owner: County
Location: Rural
Beam material: Concrete
Spans: One-span
Max Span Length (ft.): 46.67
Total Bridge Length (ft.): 46.67
Impact Category: Tier 6 (longer but reduced by months/years)
Construction Equipment Category: Conventional
Project Planning: design-bid-build,
full lane closure
Geotechnical Solutions:
Structural Solutions: adjacent box beam, precast abutment footing,
CIP reinforced closure joint, grouted key closure joint, PT ducts/bonded, socket connection (in precast substructure)-(caps)