Reset Search

2011 – Mescal Road / J Six Ranch Road Bridge
State: AZ
Year: 2011
Owner: State
Location: Rural
Beam material: Concrete
Spans: > Three-span
Max Span Length (ft.): 55
Total Bridge Length (ft.): 220.67
Impact Category: Tier 6 (longer but reduced by months/years)
Construction Equipment Category: Conventional
Project Planning: Early environmental clearance & permitting, Electronic shop drawing submittal & approval process,
Design-bid-build, Emergency contract,
Full lane closure, Accelerated bid process, Formalized partnering
Geotechnical Solutions:
Structural Solutions: Adjacent box beams,
Grouted key closure joints, PT ducts/un-bonded, Prefabricated railing

2011 – Cedar Street Bridge (Wellesley)
State: MA
Year: 2011
Owner: State
Location: Urban
Beam material: Steel
Spans: Two-span
Max Span Length (ft.): 41.54
Total Bridge Length (ft.): 83.08
Impact Category: Tier 2 (within 3 days)
Construction Equipment Category: SPMTs
Project Planning: State process, benefit/cost method,
right-of-way acquisition, electronic shop drawing submittal & approval process,
design-build,
full lane closure, incentive / disincentive clause, no excuse bonus, lump sum bonus
Geotechnical Solutions: reused substructure/foundation unit,
Structural Solutions: precast column cap (precast bent cap; precast crossbeam), precast abutment cap,
FDcBs (Full-width concrete-decked steel beam),
precast approach slab, CIP reinforced closure joint, bars in splice coupler, asphalt overlay w/membrane

2011 – Lake Champlain Bridge
State: NY
Year: 2011
Owner: State
Location: Urban
Beam material: Steel
Spans: > Three-span
Max Span Length (ft.): 480
Total Bridge Length (ft.): 2200
Impact Category: Tier 6 (longer but reduced by months/years)
Construction Equipment Category: Other ABC Method
Project Planning: early environmental clearance & permitting; electronic shop drawing submittal & approval process,
Design-Bid-Build,
Geotechnical Solutions: micropiles,
Structural Solutions: arch span w/o deck; full-depth precast deck panel w/PT; precast caisson caps,
prefabricated railing

2011 – River Road Bridge over Ironstone Brook (Uxbridge)
State: MA
Year: 2011
Owner: State
Location: Urban
Beam material: Steel
Spans: One-span
Max Span Length (ft.): 47
Total Bridge Length (ft.): 47
Impact Category: Tier 6 (longer but reduced by months/years)
Construction Equipment Category: Conventional
Project Planning: design-bid-build,
full lane closure, value engineering
Geotechnical Solutions:
Structural Solutions: MDcBs/FSPGS {Modular concrete-Decked steel Beam}, precast abutment stem, precast retaining wall,
precast curb, CIP reinforced closure joint, PT ducts/bonded, match cast closure joint, socket connection (in precast substructure), epoxy joint, micro-silica concrete overlay

2011 – I-84 Bridge F-114
State: UT
Year: 2011
Owner: State
Location: Rural
Beam material: Concrete
Spans: Three-span
Max Span Length (ft.): 55.83
Total Bridge Length (ft.): 147
Impact Category: Tier 4 (within 1 month)
Construction Equipment Category: Conventional
Project Planning: State process,
design-bid-build,
A+B+C bidding (A B C bidding), lane rental, incentive / disincentive clause, value engineering
Geotechnical Solutions:
Structural Solutions: full-depth precast deck panel w/o PT,
grouted key closure joint, grouted blockout w/shear connector, asphalt overlay w/membrane, LWC deck

2011 – I-15 / Sam White Lane Bridge
State: UT
Year: 2011
Owner: State
Location: Urban
Beam material: Steel
Spans: Two-span
Max Span Length (ft.): 177
Total Bridge Length (ft.): 354
Impact Category: Tier 1 (within 1 day)
Construction Equipment Category: SPMTs
Project Planning: State process,
design-build,
full lane closure
Geotechnical Solutions:
Structural Solutions: FDcBs (full-width concrete-decked steel beam unit),
CIP reinforced closure joint, thin-bonded epoxy overlay, LWC deck

2011 – SR 303 Manette Bridge
State: WA
Year: 2011
Owner: State
Location: Urban
Beam material: Concrete
Spans: > Three-span
Max Span Length (ft.): 250
Total Bridge Length (ft.): 1550
Impact Category: Tier 1 (within 1 day)
Construction Equipment Category: Other ABC Method
Project Planning: Design-Bid Build
Geotechnical Solutions:
Structural Solutions: Precast caisson caps,

2011 – Chester VT 103 Bridge 8
State: VT
Year: 2011
Owner: State
Location: Urban
Beam material: Concrete
Spans: One-span
Max Span Length (ft.): 56
Total Bridge Length (ft.): 56
Impact Category: Tier 4 (within 1 month)
Construction Equipment Category: Other ABC Method
Project Planning: State process,
design-bid-build,
full lane closure, incentive / disincentive clause, lump sum bonus
Geotechnical Solutions:
Structural Solutions: MDcBc {Modular concrete-Decked concrete Beam} (28D NEXT Beam), precast abutment cap, precast abutment stem, precast abutment footing,
CIP reinforced closure joint (deck), match cast closure joint (abutments), grouted key closure joint (abutments), bars in splice coupler (abutments), socket connections (abutments), epoxy joint (abutments), asphalt overlay w/membrane, precast approach slab, precast curb

2011 – US 6 Bridge over Keg Creek
State: IA
Year: 2011
Owner: State
Location: Rural
Beam material: Steel
Spans: Three-span
Max Span Length (ft.): 70
Total Bridge Length (ft.): 204.5
Impact Category: Tier 3 (within 2 weeks)
Construction Equipment Category: Conventional
Project Planning: TPF-5(221), other decision-making tool - SHRP2 R04 Toolkit,
other site procurement - precast yard in field near bridge location,
design-bid-build,
full lane closure, incentive / disincentive clause, value engineering
Geotechnical Solutions: fully-contained flooded backfill
Structural Solutions: MDcBs (Modular concrete-Decked steel Beam), precast cap & column(s), precast abutment cap, precast abutment stem, precast backwall, precast wingwall,
CIP reinforced closure joint, bars in splice coupler, socket connection (in precast substructure)-(abutments), UHPC closure joint, precast approach slab, prefabricated railing

2011 – Chester VT 103 Bridge 9
State: VT
Year: 2011
Owner: State
Location: Urban
Beam material: Concrete
Spans: One-span
Max Span Length (ft.): 119.81
Total Bridge Length (ft.): 119.81
Impact Category: Tier 5 (within 3 months)
Construction Equipment Category: Other ABC Method
Project Planning: State process,
design-bid-build,
full lane closure, incentive / disincentive clause, lump sum bonus
Geotechnical Solutions:
Structural Solutions: precast abutment cap, precast wingwall,
match cast closure joint (abutments), PT ducts/un-bonded (abutments), socket connection (abutments), epoxy joint (abutments), asphalt overlay w/membrane, precast approach slab