
2011 – Volmer and Johnson Creek Bridges
State: OR
Year: 2011
Owner: State
Location: Rural
Beam material: Concrete
Spans: One-span
Max Span Length (ft.): 29
Total Bridge Length (ft.): 29
Impact Category: Tier 4 (within 1 month)
Construction Equipment Category: Conventional
Project Planning: State process,
Design-bid-build,
Geotechnical Solutions:
Structural Solutions: adjacent slab beam; precast abutment cap w/backwall; steel sheet piling,
grouted key closure joint; socket connection (in precast substructure); epoxy joint; asphalt overlay w/membrane; precast approach slab; precast curb; other miscellaneous prefabricated element – precast sleeper slab; other miscellaneous prefabricated element – precast shear lugs

2011 – US 6 Bridge over Keg Creek
State: IA
Year: 2011
Owner: State
Location: Rural
Beam material: Steel
Spans: Three-span
Max Span Length (ft.): 70
Total Bridge Length (ft.): 204.5
Impact Category: Tier 3 (within 2 weeks)
Construction Equipment Category: Conventional
Project Planning: TPF-5(221), other decision-making tool - SHRP2 R04 Toolkit,
other site procurement - precast yard in field near bridge location,
design-bid-build,
full lane closure, incentive / disincentive clause, value engineering
Geotechnical Solutions: fully-contained flooded backfill
Structural Solutions: MDcBs (Modular concrete-Decked steel Beam), precast cap & column(s), precast abutment cap, precast abutment stem, precast backwall, precast wingwall,
CIP reinforced closure joint, bars in splice coupler, socket connection (in precast substructure)-(abutments), UHPC closure joint, precast approach slab, prefabricated railing

2011 – UPRR Bridge 126.31
State: KS
Year: 2011
Owner: Union Pacific Railroad (UPRR)
Location: Rural
Beam material: Concrete
Spans: > Three-span
Max Span Length (ft.): 29.83
Total Bridge Length (ft.): 150
Impact Category: Tier 1 (within 1 day)
Construction Equipment Category: Other ABC Method
Project Planning: design-bid-build,
full lane closure (i.e., full track closure)
Geotechnical Solutions:
Structural Solutions: adjacent box beam, precast pile cap, precast abutment cap w/backwall, precast wingwall,
prefabricated railing

2011 – TH 61 Bridge over Gilbert Creek
State: MN
Year: 2011
Owner: State
Location: Rural
Beam material: Concrete
Spans: Three-span
Max Span Length (ft.): 41
Total Bridge Length (ft.): 123
Impact Category: Tier 5 (within 3 months)
Construction Equipment Category: Conventional
Project Planning: design-bid-build,
A+B bidding (A B bidding), incentive / disincentive clause
Geotechnical Solutions:
Structural Solutions: adjacent inverted T beam, precast pile cap, precast abutment stem, precast wingwall,
CIP reinforced closure joint, socket connection (in precast substructure), thin-bonded epoxy overlay

2011 – South Punaluu Stream Bridge
State: HI
Year: 2011
Owner: State
Location: Rural
Beam material: Concrete
Spans: Three-span
Max Span Length (ft.): 66
Total Bridge Length (ft.): 170
Impact Category: Tier 6 (longer but reduced by months/years)
Construction Equipment Category: Conventional
Project Planning: design-bid-build,
full lane closure, value engineering
Geotechnical Solutions:
Structural Solutions: adjacent T beams; MDcBc (Modular decked beam – precast decked tub beam),
grouted key closure joints

2011 – Salem Street Bridge Eastbound (93Fast14)
State: MA
Year: 2011
Owner: State
Location: Urban
Beam material: Steel
Spans: Three-span
Max Span Length (ft.): 78
Total Bridge Length (ft.): 160
Impact Category: Tier 2 (within 3 days)
Construction Equipment Category: Other ABC Method
Project Planning: State process,
early environmental clearance & permitting, electronic shop drawing submittal & approval process,
design-build,
full lane closure, warranty, incentive / disincentive clause, no excuse bonus, value engineering
Geotechnical Solutions: reused substructure/foundation unit,
Structural Solutions: MDcBs (modular concrete-decked steel beams),
CIP reinforced closure joint, HESt-LSh concrete joint {high-early-strength low-shrinkage concrete joint}, link slab, asphalt overlay w/membrane

2011 – River Road Bridge over Ironstone Brook (Uxbridge)
State: MA
Year: 2011
Owner: State
Location: Urban
Beam material: Steel
Spans: One-span
Max Span Length (ft.): 47
Total Bridge Length (ft.): 47
Impact Category: Tier 6 (longer but reduced by months/years)
Construction Equipment Category: Conventional
Project Planning: design-bid-build,
full lane closure, value engineering
Geotechnical Solutions:
Structural Solutions: MDcBs/FSPGS {Modular concrete-Decked steel Beam}, precast abutment stem, precast retaining wall,
precast curb, CIP reinforced closure joint, PT ducts/bonded, match cast closure joint, socket connection (in precast substructure), epoxy joint, micro-silica concrete overlay

2011 – Mescal Road / J Six Ranch Road Bridge
State: AZ
Year: 2011
Owner: State
Location: Rural
Beam material: Concrete
Spans: > Three-span
Max Span Length (ft.): 55
Total Bridge Length (ft.): 220.67
Impact Category: Tier 6 (longer but reduced by months/years)
Construction Equipment Category: Conventional
Project Planning: Early environmental clearance & permitting, Electronic shop drawing submittal & approval process,
Design-bid-build, Emergency contract,
Full lane closure, Accelerated bid process, Formalized partnering
Geotechnical Solutions:
Structural Solutions: Adjacent box beams,
Grouted key closure joints, PT ducts/un-bonded, Prefabricated railing

2011 – Little Cedar Creek Bridge
State: IA
Year: 2011
Owner: County
Location: Rural
Beam material: Concrete
Spans: One-span
Max Span Length (ft.): 60
Total Bridge Length (ft.): 60
Impact Category: Tier 5 (within 3 months)
Construction Equipment Category: Conventional
Project Planning: design-bid-build,
full lane closure
Geotechnical Solutions: fully-contained flooded backfill
Structural Solutions: UHPC waffle deck,
CIP reinforced closure joint, UHPC closure joint, grouted blockout w/shear connector

2011 – Lake Champlain Bridge
State: NY
Year: 2011
Owner: State
Location: Urban
Beam material: Steel
Spans: > Three-span
Max Span Length (ft.): 480
Total Bridge Length (ft.): 2200
Impact Category: Tier 6 (longer but reduced by months/years)
Construction Equipment Category: Other ABC Method
Project Planning: early environmental clearance & permitting; electronic shop drawing submittal & approval process,
Design-Bid-Build,
Geotechnical Solutions: micropiles,
Structural Solutions: arch span w/o deck; full-depth precast deck panel w/PT; precast caisson caps,
prefabricated railing

