2012 – TH 53 Bridge over Paleface River

State: MN
Year: 2012
Owner: State
Location: Rural
Beam material: Concrete

Spans: One-span
Max Span Length (ft.): 75
Total Bridge Length (ft.): 75
Impact Category: Tier 5 (within 3 months)
Construction Equipment Category: Conventional

Project Planning: design-bid-build, full lane closure, incentive / disincentive clause
Geotechnical Solutions:
Structural Solutions: full-depth precast deck panel w/PT, CIP reinforced closure joint, grouted key closure joint, PT ducts/bonded, thin-bonded epoxy overlay


2012 – Route 202 Bridge over Passaic River

State: NJ
Year: 2012
Owner: State
Location: Urban
Beam material: Steel

Spans: One-span
Max Span Length (ft.): 92
Total Bridge Length (ft.): 92
Impact Category: Tier 3 (within 2 weeks)
Construction Equipment Category: Conventional

Project Planning: design-bid-build, full lane closure
Geotechnical Solutions:
Structural Solutions: MDcBs (modular concrete-decked steel beams), precast abutment cap, precast backwall, precast wingwall, CIP reinforced closure joint, socket connection (in precast substructure), asphalt overlay w/o membrane, precast approach slab, prefabricated railing, other miscellaneous element – precast sleeper slab


2012 – Maryland Avenue Bridge

State: MN
Year: 2012
Owner: State
Location: Urban
Beam material: Concrete

Spans: Two-span
Max Span Length (ft.): 102.75
Total Bridge Length (ft.): 210.5
Impact Category: Tier 5 (within 3 months)
Construction Equipment Category: SPMTs

Project Planning: design-build, best value award
Geotechnical Solutions: EPS geofoam
Structural Solutions: FDcBc {Full-Width concrete-Decked concrete Beam Unit}, thin-bonded epoxy overlay


2012 – Rock County Road 55 Bridge over Railroad

State: MN
Year: 2012
Owner: Rock County
Location: Rural
Beam material: Concrete

Spans: One-span
Max Span Length (ft.): 82.5
Total Bridge Length (ft.): 82.5
Impact Category: Tier 5 (within 3 months)
Construction Equipment Category: Conventional

Project Planning: design-bid-build,
Geotechnical Solutions: GRS IBS [Geosynthetic Reinforced Soil Integrated Bridge System],
Structural Solutions: adjacent box beams, GRS abutments, asphalt overlay w/o membrane


2012 – Burnt River & UPRR Bridge

State: OR
Year: 2012
Owner: State
Location: Rural
Beam material: Concrete

Spans: One-span
Max Span Length (ft.): 160
Total Bridge Length (ft.): 160
Impact Category: Tier 6 (longer but reduced by months/years)
Construction Equipment Category: Conventional

Project Planning: State process, Design-bid-build, Full lane closure
Geotechnical Solutions:
Structural Solutions: Full-depth precast deck panel w/o PT; MSE walls, CIP reinforced concrete closure joints; Grouted blockout w/shear connectors; UHPC closure joints


2011 – Uxbridge –River Road Bridge over Ironstone Brook

State: MA
Year: 2011
Owner: State
Location: Urban
Beam material: Steel

Spans: One-span
Max Span Length (ft.): 47
Total Bridge Length (ft.): 47
Impact Category: Tier 6 (longer but reduced by months/years)
Construction Equipment Category: Conventional

Project Planning: design-bid-build, full lane closure, value engineering
Geotechnical Solutions:
Structural Solutions: MDcBs/FSPGS {Modular concrete-Decked steel Beam}, precast abutment stem, precast retaining wall, CIP reinforced concrete closure joint, PT ducts/bonded, match cast closure joint, socket connection (in precast substructure), epoxy joint, micro-silica concrete overlay, precast curb


2011 – I-84 Bridge F-114

State: UT
Year: 2011
Owner: State
Location: Rural
Beam material: Concrete

Spans: Three-span
Max Span Length (ft.): 55.83
Total Bridge Length (ft.): 147
Impact Category: Tier 4 (within 1 month)
Construction Equipment Category: Conventional

Project Planning: State process, design-bid-build, A+B+C bidding, lane rental, incentive / disincentive clause, value engineering
Geotechnical Solutions:
Structural Solutions: full-depth precast deck panel w/o PT, grouted key closure joint, grouted blockout w/shear connector, asphalt overlay w/membrane, LWC deck


2011 – I-15 / Sam White Lane Bridge

State: UT
Year: 2011
Owner: State
Location: Urban
Beam material: Steel

Spans: Two-span
Max Span Length (ft.): 177
Total Bridge Length (ft.): 354
Impact Category: Tier 1 (within 1 day)
Construction Equipment Category: SPMTs

Project Planning: State process, design-build, full lane closure
Geotechnical Solutions:
Structural Solutions: FDcBs (full-width concrete-decked steel beam unit), CIP reinforced closure joint, thin-bonded epoxy overlay, LWC deck


2011 – SR 303 Manette Bridge

State: WA
Year: 2011
Owner: State
Location: Urban
Beam material: Concrete

Spans: > Three-span
Max Span Length (ft.): 250
Total Bridge Length (ft.): 1550
Impact Category: Tier 1 (within 1 day)
Construction Equipment Category: Other ABC Method

Project Planning: Design-Bid Build
Geotechnical Solutions:
Structural Solutions: Precast caisson caps,


2011 – Chester VT 103 Bridge 8

State: VT
Year: 2011
Owner: State
Location: Urban
Beam material: Concrete

Spans: One-span
Max Span Length (ft.): 56
Total Bridge Length (ft.): 56
Impact Category: Tier 4 (within 1 month)
Construction Equipment Category: Other ABC Method

Project Planning: State process, design-bid-build, full lane closure, incentive / disincentive clause, lump sum bonus
Geotechnical Solutions:
Structural Solutions: MDcBc {Modular concrete-Decked concrete Beam} (28D NEXT Beam), precast abutment cap, precast abutment stem, precast abutment footing, CIP reinforced closure joint (deck), match cast closure joint (abutments), grouted key closure joint (abutments), bars in splice coupler (abutments), socket connections (abutments), epoxy joint (abutments), asphalt overlay w/membrane, precast approach slab, precast curb