2004 – Nemo Bridge (Route 64 over Lindley Creek)

Year ABC Built: 2004
State: MO
County: Hickory
Owner: State
Location: Rural
Spans: > Three-span
Beam material: Steel
Max Span Length (ft.): 90
Total Bridge Length (ft.): 1684
Construction Equipment Category: Conventional
ABC Construction Equipment: Conventional
State ID Number: A0894
NBI Number: 649
Coordinates
Latitude:
37.8650000 | Longitude: -93.2816667
{"autoplay":"true","autoplay_speed":"4000","speed":"300","arrows":"true","dots":"true","rtl":"false"}

Under Construction


Bridge Description

Project Summary:

Deck replacement using full-depth precast concrete deck panels with transverse post-tensioning.


Project Location:

on Route 64 over the Lindley Creek arm of the Pomme De Terre Lake near the town of Nemo in the Missouri Ozarks


Impact Category:

Tier 6 (longer but reduced by months/years)


Mobility Impact Time:
  • ABC: 3 months of overnight closures; 1 month of one-lane closures
  • Conventional: 2 years of one-lane closures


Primary Drivers:
  • reduced traffic impacts
  • reduced onsite construction time
  • improved site constructability


Dimensions:

1,684-ft long and 27.5-ft wide 19-span five-unit (275 ft - 360 ft - 360 ft - 360 ft - 329 ft) composite steel I-girder bridge [seventeen 90-ft-long spans & two 75-ft-long spans]


Average Daily Traffic (at time of construction):

3290


Traffic Management:

two years of one-lane closures; 28-mile detour


Existing Bridge Description:

The existing two-lane 22-ft-wide bridge had two 11-ft-wide traffic lanes. The cross-section consists of four 3-ft-deep steel I-girders at 6.67-ft spacing, with a 7-inch-thick composite reinforced concrete deck. Built in 1960 by the US Army Corps of Engineers, the bridge had a deteriorated deck that was too narrow and required replacement.


Replacement or New Bridge:

Deck replacement on existing bridge


Construction Method:

The contractor cast the 162 precast deck panels on a 29-ft by 360-ft casting bed adjacent to the bridge site. The 10-ft-long segments of 27.5-ft-wide, 9-inch-thick panels with epoxy-coated reinforcement were match cast for the entire length of each of the five continuous sections between expansion joints. The project also included replacing expansion joints, re-painting the steel girders, and replacing the abutment backwalls.

 

During nighttime closures, the contractor removed an old deck section, removed the old shear studs and painted the tops of the girders, coated the match-cast panel edge with epoxy, set the panel, and repeated the process. After panels were set, shear studs were welded to the girders in the blockout locations. Adjacent panels were post-tensioned together with eight 1-inch-diameter epoxy-coated bars, and haunches and blockouts were filled with fast-setting grout cast through the blockout openings. The contractor set from 30 ft to 80 ft of panels each night. A short transition length was left between the panels and existing deck using steel grid as the temporary riding surface.

 

Cast-in-place closure joints connected the panels and the new expansion joints. The bridge was opened to traffic when the grout reached 2,500 psi. The post-tensioning ducts were grouted at a later date.

 

The traffic barrier was slip-formed after all panels were erected during one-lane closures after Labor Day. Similarly, the 1.5-inch-thick micro-silica overlay was placed half-width at night during one-lane closures after Labor Day.

 

The contract required that the bridge be closed only on Sunday through Thursday from 7 pm to 7 am between the Memorial Day weekend and the Labor Day weekend. The contract also included a disincentive of $143 for every five minutes that the lanes were opened late. The contract also required that the bridge be opened by the November 30, 2004 completion date, to avoid liquidated damages of $2,300 per day.


Stakeholder Feedback:

MoDOT anticipates the new panels, the new expansion joints, and the rehabilitation and painting of the steel girders will add another 50 years to the bridge’s service life. In addition, MODOT believes that the significant reduction in construction time was greatly appreciated by the public due to the 28 mile detour.

 

MoDOT was pleased with the outcome of this project; However, because of funding restraints and the higher cost of this type of deck replacement, we have not been able to use this application in other locations.


High Performance Material:
  • 7000 psi expanding grout
  • quick drying organic zinc primer


Project Planning

Decision Making Tools: State process
Site Procurement: right–of-way acquisition (for dock easement only)
Project Delivery: design-bid-build
Contracting: full lane closure, Incentive / disincentive clause

Geotechnical Solutions

Foundations & Walls:
Rapid Embankment:

Structural Solutions

Prefabricated Bridge Elements: full-depth precast deck panel w/PT
Prefabricated Bridge Systems:
Miscellaneous Prefabricated: CIP reinforced closure joint, grouted blockout w/shear connector, PT ducts/bonded, match cast closure joint, micro-silica concrete overlay

Costs & Funding

Costs:

The engineer’s estimate for the project was $ 5.343 million. The low bid was $5.51 million ($178,000 = 3.14% higher than engineer’s estimate). There were 3 bidders. The cost per square foot of bridge was $98.25 compared to $60 for conventional construction in this region in 2004.

 

ABC techniques saved an estimated $230 thousand in delay-related user costs. The net additional cost on the project totaled approximately $1.77 million or 63 percent over conventional construction.


Funding Source:

Federal Only


Incentive Program:

IBRC (Innovative Bridge Research and Construction Program): $160,000



Additional Information



Contacts

Owner:
Bryan A. Hartnagel, P.E., Ph.D.
State Bridge Engineer
Missouri Department of Transportation
Email: Bryan.Hartnagel@modot.mo.gov
Phone: 573-751-4676

Designer:
HNTB

Submitter:
Mary Lou Ralls, P.E.
Principal
Ralls Newman, LLC
Email: ralls-newman@sbcglobal.net
Phone: 512-422-9080