Accelerated Bridge Construction
University Transportation Center

ABC Project and Research Databases

2011 – Buffalo Creek Bridge

Year ABC Built: 2011
State: SD
County:
Owner: Perkins County
Location: Rural
Spans: One-span
Beam material: Concrete
Max Span Length (ft.): 60
Total Bridge Length (ft.): 60
Construction Equipment Category: Conventional
ABC Construction Equipment: Conventional
State ID Number: 53-048-010
NBI Number: 53048010
Coordinates
Latitude:
45.9358711 | Longitude: -100
{"autoplay":"true","autoplay_speed":"4000","speed":"300","arrows":"true","dots":"true","rtl":"false"}

Under Construction


Bridge Description

Project Summary:


Project Location:

Border Line Road over Buffalo Creek approximately 24 miles west of the town of White Butte in Perkins County


Impact Category:

Tier 6 (longer but reduced by months/years)


Mobility Impact Time:

ABC: NA; Conventional: This type construction is typical for local SD roads


Primary Drivers:

reduced traffic impacts; reduced onsite construction time; improved site constructability; minimized environmental impacts


Dimensions:

60-ft-long and 30.67-ft-wide single-span adjacent T beam (prestressed double tee) bridge


Average Daily Traffic (at time of construction):

60


Traffic Management (if constructed conventionally):

Traffic management alternative: Onsite short detour


Existing Bridge Description:

The existing single-span bridge was deteriorated and required replacement.


Replacement or New Bridge:

The replacement bridge has a 28-ft-wide roadway width. The cross-section consists of eight 3.83-ft-wide 30-inch-deep pretensioned double tee beams. The vertical abutments are founded on tied-back H-piles with10-gauge galvanized steel sheet piling backwalls, and precast concrete planks at the ends of the beams.


Construction Method:

The pretensioned double tee beams were fabricated at a precast plant and shipped to the bridge site. The two exterior beams were cast with Type T101 rail post connection steel. The eight beams weigh approximately 16 tons each.The bridge was closed and traffic detoured. Excavation was completed and H-piles were driven at each abutment location. The sheet pile backwalls and wingwalls were erected and tie-back cables were anchored to steel piling driven in undisturbed soil behind the abutments. Steel pile caps were erected onto the H-piles and the bearing dowel bars were welded to the bottom flange. The double tee beams were erected onto elastomeric bearing pads. A dowel pin was placed through the beam end and steel cap top flange and welded. The beams were also welded together at 5-ft spacing longitudinally. The 3-inch x 27-inch precast concrete planks were bolted to the ends of the beams.The shear keys between beams and the dowel bars were filled with non-shrink grout. The 7-inch x 4-inch x 5-inch blockouts at the ends of the beams were filled with grout. Railing was installed. No overlay was applied. The bridge was opened to traffic.No incentives/disincentives or other contracting strategies to achieve rapid construction were used on this project. The schedule was driven by the contractor’s availability and work load.


Stakeholder Feedback:

This bridge is an example of the prefabricated bridges commonly used on the South Dakota local road system. It is an example of the use of PBES that could have been done in an accelerated manner. However, there were no requirements at this location for accelerated construction. The use of PBES was driven more due to the remote location and lack of ready-mix concrete availability.


High Performance Material:

Project Planning

Decision Making Tools:
Site Procurement:
Project Delivery: Design-bid-build
Contracting: Full lane closure

Geotechnical Solutions

Foundations & Walls:
Rapid Embankment:

Structural Solutions

Prefabricated Bridge Elements: Adjacent T beams (double tee); Steel sheet piling; Other abutment element: precast planks
Prefabricated Bridge Systems:
Miscellaneous Prefabricated: Grouted key closure joints

Costs & Funding

Costs:

The engineer’s estimate for the project was $ 413,000. The low bid was $459,000. There were four bidders. The cost per square foot of bridge was $136 compared to $141 for conventional construction in this region in 2011.


Funding Source:

Other


Incentive Program:

(Federal and Local)



Additional Information


Downloadable Resources

Contract Plans:

View H119Plans.pdf

Specifications:

Bid Tabs:

View BidTabH119.pdf

Construction Schedule:


Other Related Information:

Summary Sheet:
121113-ABC_New2_SD_2011_Buffalo-Creek


Other Related URLs:


Photo Credits:

South Dakota Department of Transportation


Contacts

Kevin Goeden, P.E.
Chief Bridge Engineer
South Dakota Department of Transportation
kevin.goeden@state.sd.us
605-773-3285