Accelerated Bridge Construction
University Transportation Center

ABC Project and Research Databases

2010 – 41st Street Bridge

Year ABC Built: 2010
State: SD
County:
Owner: City of Sioux Falls
Location: Urban
Spans: Three-span
Beam material: Concrete
Max Span Length (ft.): 125
Total Bridge Length (ft.): 305
Construction Equipment Category: Conventional
ABC Construction Equipment: Conventional
State ID Number: 50-183-230
NBI Number: 50183230
Coordinates
Latitude:
43.5147972 | Longitude: -96.7656784
{"autoplay":"true","autoplay_speed":"4000","speed":"300","arrows":"true","dots":"true","rtl":"false"}

Under Construction


Bridge Description

Project Summary:


Project Location:

41st Street over the Big Sioux River in the City of Sioux Falls in Minnehaha County


Impact Category:

Tier 6 (longer but reduced by months/years)


Mobility Impact Time:

ABC: 113 days with two-stage construction ; Conventional: one year with two-stage construction


Primary Drivers:

reduced traffic impacts – critical arterial; improved site constructability – no deck forming required


Dimensions:

305-ft-long and 112.33-ft wide three-span bridge (90 ft - 125 ft - 87 ft)


Average Daily Traffic (at time of construction):

47000


Traffic Management (if constructed conventionally):

Traffic management alternative, if constructed conventionally: extended use of detours onto city streets


Existing Bridge Description:

The existing six-lane, three-span bridge was 282-ft-long and 106.83-ft-wide with 15 steel I-beams at 6.5 ft and 7.0 ft spacing per span. Built in 1965, and widened at a later date, the bridge is located in the city’s business district on the busiest street in the state of South Dakota, the bridge was initially to be replaced by the US Army Corps of Engineers as part of a flood control project to improve the safety of the levee along the Big Sioux River. Because of its deteriorated condition and potential impact on traffic, the City of Sioux Falls decided to replace it with accelerated methods, ahead of the levee project.


Replacement or New Bridge:

The seven-lane replacement bridge has 19 adjacent precast pretensioned concrete box beams per span, with a composite 5.5-inch-thick cast-in-place concrete deck. The Colorado DOT standard box beams were 4.5 ft deep and 5 ft and 6 ft wide. The cross-section also included 4-ft outside shoulders as well as sidewalks separated from traffic lanes by concrete barriers.


Construction Method:

The bridge was constructed in two stages with two 11-ft-wide lanes of traffic in each direction maintained during each stage. The steel H-pile concrete-encased wall piers were constructed prior to removal of the existing piers to speed construction. The integral abutment was founded on a single row of H-piles. The adjacent beams were erected and transversely post-tensioned with tie-rods. The deck was cast end-to-end with no transverse joints; the deck was cast at the minimum rate of 40 cu yds per hr using a set retarder. A full-depth concrete closure joint was cast between the stages of construction.The contract required completion of the bridge within 160 days for the bid to be responsive. The incentive was set at five to six percent of the estimated cost, for a maximum incentive of $500,000. The contract included a $250,000 lump-sum incentive payment if the project was completed within the number of days bid in the awarded contract. An additional $10,000 incentive was included for each day the project was completed earlier than the number of days bid.The awarded contractor bid 140 days. The actual construction duration of 113 days resulted in a 70% time savings compared to conventional construction. The contractor received the maximum incentive of $500,000.


Stakeholder Feedback:

The adjacent box beams were a new beam for the state of South Dakota. The local fabricator commented that since they constructed the precast box girder for this project, the learning curve for these types of precast members is reduced and would they would readily bid these types of structures on future projects. Also, the contractor stated that adding a precast overhang would have accelerated construction, although costs would not likely have been reduced.


High Performance Material:

Project Planning

Decision Making Tools:
Site Procurement:
Project Delivery: Design-bid-build
Contracting: A+B bidding; Incentive / disincentive clauses; Lump sum

Geotechnical Solutions

Foundations & Walls:
Rapid Embankment:

Structural Solutions

Prefabricated Bridge Elements: Adjacent box beams
Prefabricated Bridge Systems:
Miscellaneous Prefabricated: Grouted key closure joints; PT ducts/bonded

Costs & Funding

Costs:

The engineer’s estimate for the project was $5.7 million (bridge replacement). The low bid was $4.4 million ($1.3 = 30% lower than the engineer’s estimate). There were five bidders. The cost per square foot of bridge was $127 compared to $85-$100 for conventional construction in this region in 2010.


Funding Source:

Other


Incentive Program:

(City of Sioux Falls)



Additional Information


Downloadable Resources

Contract Plans:

View 41st_Sioux_Falls_Bridge_Plans.pdf

Specifications:

View 41st_Specifications_09-1105.pdf

Bid Tabs:

View 41st_Bridge_Bids.pdf

Construction Schedule:

View 41st_Bridge_Engineers_Schedule_Prelim_Study.pdf


Other Related Information:

2011-PCI-NBC-Paper-57
Summary Sheet:
130124-ABC_New2_SD_2010_41st-Street


Other Related URLs:


Photo Credits:

City of Sioux Falls


Contacts

Josh Peterson, P.E.
Principal Engineer
City of Sioux Falls
jpeterson@siouxfalls.org
605-367-8616