Category: Completed Projects
Group: Design-Making Tools
Subject: AHP
State: Oregon Abstract: In this FHWA-sponsored pool funded study, a set of decision making tools, based on the Analytic Hierarchy Process (AHP) was developed. This tool set is prepared for transportation specialists and decision-makers to determine if ABC is more effective than traditional construction for a given bridge replacement or rehabilitation project. The tool set is user-friendly, flexible to accommodate a range of construction situations, transparent as to the method of calculation, and customizable to maintain future relevance. To accommodate this task, a comprehensive literature review on a number of relevant domains such as ABC construction techniques and decision making approaches, were completed. The findings were summarized into a decision model hierarchy that was also incorporated into the decision making software. The software was tested through evaluating a set of real-world construction projects.
Key Words: Accelerated Bridge Construction, Decision Making, AHP, Criteria Hierarchy
Specific ABC aspect:
Budget (USD): 120000.00
Project length: 18
Project Starting Year: 2009
Project Completion Year: 2011
View ABC-Decision-Making-and-Economic-Modeling-Tools-Final-Report.pdf
Go to: https://www.pooledfund.org/Details/Study/449
Group: Design-Making Tools
Subject: AHP
State: Oregon Abstract: In this FHWA-sponsored pool funded study, a set of decision making tools, based on the Analytic Hierarchy Process (AHP) was developed. This tool set is prepared for transportation specialists and decision-makers to determine if ABC is more effective than traditional construction for a given bridge replacement or rehabilitation project. The tool set is user-friendly, flexible to accommodate a range of construction situations, transparent as to the method of calculation, and customizable to maintain future relevance. To accommodate this task, a comprehensive literature review on a number of relevant domains such as ABC construction techniques and decision making approaches, were completed. The findings were summarized into a decision model hierarchy that was also incorporated into the decision making software. The software was tested through evaluating a set of real-world construction projects.
Key Words: Accelerated Bridge Construction, Decision Making, AHP, Criteria Hierarchy
Specific ABC aspect:
Budget and Timeline
Budget (USD): 120000.00
Project length: 18
Project Starting Year: 2009
Project Completion Year: 2011
Primary Sponsor
Sponsor #1:
Oregon Department of Transportation (lead in pooled fund study)
355 Capitol Street NE
Salem, OR 97301 USA
Sponsor #1 Contact: Benjamin Tang
Sponsor #2:
Federal Highway Administration
400 Seventh Street, SW
Washington, DC 20590
Primary Performing Organization
Oregon State University
Department of Civil Engineering
Corvallis, OR 97331 USA
PI: Amirali Saeedi
Co-PI: Toni Doolen
Dean of University Honors College
541.737.5974
Toni.Doolen@oregonstate.edu