*Note: For keyword searches, use Keywords for Database Search with quotes (example: “Full-Depth Precast Deck Panel w/o PT”).
Reset Search
Found 8 Results

2013 – I-5 / Skagit River Bridge Span 8 Replacement

State: WA
Year: 2013
Owner: State
Location: Rural
Beam material: Concrete

Spans: > Three-span
Max Span Length (ft.): 163
Total Bridge Length (ft.): 1111.75
Impact Category: Tier 1 (within 1 day)
Construction Equipment Category: Lateral Slide

Project Planning: (1) Emergency Contract - used to remove collapsed span and construct temporary Acrow span. (2) Design-Build Contract - used to construct permanent span and slide temporary and permanent spans., A+B+C bidding
Geotechnical Solutions: Reused Substructure/Foundation Unit,
Structural Solutions: Adjacent deck bulb T beams, FDcBc (full-width concrete-decked concrete beam unit) - total superstructure span slid into place on existing foundation, LWC beams; high-strength CIP reinforced closure joint; micro-silica concrete overlay


2011 – I-5 / US 12 Bridge at Grand Mound

State: WA
Year: 2011
Owner: State
Location: Urban
Beam material: Concrete

Spans: Two-span
Max Span Length (ft.): 88
Total Bridge Length (ft.): 176
Impact Category: Tier 5 (within 3 months)
Construction Equipment Category: Conventional

Project Planning: Design-bid-build,
Geotechnical Solutions:
Structural Solutions: Adjacent deck bulb T beams; Precast cap & column(s), CIP reinforced concrete closure joints; Grouted key closure joints; Grouted duct connection (in precast substructure); Precast diaphragms


2011 – SR 303 Manette Bridge

State: WA
Year: 2011
Owner: State
Location: Urban
Beam material: Concrete

Spans: > Three-span
Max Span Length (ft.): 250
Total Bridge Length (ft.): 1550
Impact Category: Tier 1 (within 1 day)
Construction Equipment Category: Other ABC Method

Project Planning: Design-Bid Build
Geotechnical Solutions:
Structural Solutions: Precast caisson caps,


2007 – SR 520 / SR 202 Interchange

State: WA
Year: 2007
Owner: State
Location: Urban
Beam material: Concrete

Spans: Three-span
Max Span Length (ft.): 145
Total Bridge Length (ft.): 435
Impact Category: Tier 5 (within 3 months)
Construction Equipment Category: Other ABC Method

Project Planning: Design-Bid-Build, Contractor option
Geotechnical Solutions:
Structural Solutions: Precast column cap (precast bent cap; precast crossbeam); grouted duct connection,


2005 – Hood Canal Bridge (East Approach Spans)

State: WA
Year: 2005
Owner: State
Location: Rural
Beam material: Concrete

Spans: > Three-span
Max Span Length (ft.): 125
Total Bridge Length (ft.): 605
Impact Category: Tier 2 (within 3 days)
Construction Equipment Category: Lateral Slide

Project Planning: design-bid-build,
Geotechnical Solutions: CIP substructure under traffic,
Structural Solutions: precast backwall, FDcBc (Full-width concrete-decked concrete beam unit), CIP reinforced concrete closure joint; precast approach slab


2004 – Lewis and Clark Bridge

State: WA
Year: 2004
Owner: State
Location: Urban
Beam material: Steel

Spans: > Three-span
Max Span Length (ft.): 1200
Total Bridge Length (ft.): 5478
Impact Category: Tier 2 (within 3 days)
Construction Equipment Category: SPMTs

Project Planning: Design-bid-build, A+B+C bidding; Full lane closure; Lane rental; Incentive / disincentive clauses; Contractor revision
Geotechnical Solutions:
Structural Solutions: Full-depth precast deck panel w/o PT, CIP reinforced concrete closure joints; Grouted key closure joint; Micro-silica concrete overlay; Precast approach slabs; Prefabricated railing


2003 – I-405 / Northeast 8th Street Bridge

State: WA
Year: 2003
Owner: State
Location: Urban
Beam material: Steel

Spans: Two-span
Max Span Length (ft.): 164
Total Bridge Length (ft.): 328
Impact Category: Tier 2 (within 3 days)
Construction Equipment Category: Lateral Slide

Project Planning: Design-bid-build, Incentive / disincentive clauses
Geotechnical Solutions:
Structural Solutions: FDcBs (Full-width concrete-decked steel beam unit, CIP reinforced concrete closure joints


2001 – I-5 / South 38th Street Bridge

State: WA
Year: 2001
Owner: State
Location: Urban
Beam material: Concrete

Spans: Two-span
Max Span Length (ft.): 164.25
Total Bridge Length (ft.): 325
Impact Category: Tier 6 (longer but reduced by months/years)
Construction Equipment Category: Conventional

Project Planning: • Design-bid-build, • Full lane closure• Incentive / disincentive clause
Geotechnical Solutions:
Structural Solutions: • Partial-depth precast deck panels,