2012 – OR213 Bridge over Washington Street (Jughandle)

State: OR
Year: 2012
Owner: State
Location: Urban
Beam material: Steel

Spans: One-span
Max Span Length (ft.): 130
Total Bridge Length (ft.): 130
Impact Category: Tier 3 (within 2 weeks)
Construction Equipment Category: Lateral Slide

Project Planning: State process, Design-bid-build, Full lane closure; Best value award
Geotechnical Solutions:
Structural Solutions: FDcBs (Full-width concrete-decked steel beam unit, CIP reinforced concrete closure joints


2012 – Burnt River & UPRR Bridge

State: OR
Year: 2012
Owner: State
Location: Rural
Beam material: Concrete

Spans: One-span
Max Span Length (ft.): 160
Total Bridge Length (ft.): 160
Impact Category: Tier 6 (longer but reduced by months/years)
Construction Equipment Category: Conventional

Project Planning: State process, Design-bid-build, Full lane closure
Geotechnical Solutions:
Structural Solutions: Full-depth precast deck panel w/o PT; MSE walls, CIP reinforced concrete closure joints; Grouted blockout w/shear connectors; UHPC closure joints


2011 – Volmer and Johnson Creek Bridges

State: OR
Year: 2011
Owner: State
Location: Rural
Beam material: Concrete

Spans: One-span
Max Span Length (ft.): 29
Total Bridge Length (ft.): 29
Impact Category: Tier 4 (within 1 month)
Construction Equipment Category: Conventional

Project Planning: State process, Design-bid-build,
Geotechnical Solutions:
Structural Solutions: adjacent slab beam; precast abutment cap w/backwall; steel sheet piling, grouted key closure joint; socket connection (in precast substructure); epoxy joint; asphalt overlay w/membrane; precast approach slab; precast curb; other miscellaneous prefabricated element – precast sleeper slab; other miscellaneous prefabricated element – precast shear lugs


2008 – Elk Creek Bridge (Crossing No. 3)

State: OR
Year: 2008
Owner: State
Location: Rural
Beam material: Steel

Spans: Three-span
Max Span Length (ft.): 207.5
Total Bridge Length (ft.): 320.5
Impact Category: Tier 2 (within 3 days)
Construction Equipment Category: Lateral Slide

Project Planning: State process, early environmental clearance & permitting, design-build, full lane closure, incentive / disincentive clause
Geotechnical Solutions: CIP substructure under traffic,
Structural Solutions: precast wingwall, FDcBs (full-width concrete-decked steel beam unit), CIP reinforced closure joint, precast approach slab, other miscellaneous prefabricated element – precast sleeper slab


2008 – Kimberly Bridge

State: OR
Year: 2008
Owner: State
Location: Rural
Beam material: Concrete

Spans: One-span
Max Span Length (ft.): 42
Total Bridge Length (ft.): 42
Impact Category: Tier 3 (within 2 weeks)
Construction Equipment Category: Conventional

Project Planning: State process, design-bid-build, full lane closure
Geotechnical Solutions:
Structural Solutions: adjacent slab beam, precast abutment cap, grouted key closure joint, socket connection (in precast substructure), asphalt overlay w/membrane (Spans 1 & 5 only), precast curb


2007 – OR 47 Bridge over Dairy Creek Overflow

State: OR
Year: 2007
Owner: State
Location: Rural
Beam material: Concrete

Spans: One-span
Max Span Length (ft.): 45
Total Bridge Length (ft.): 45
Impact Category: Tier 3 (within 2 weeks)
Construction Equipment Category: Conventional

Project Planning: State process, In-house forces, Full lane closure
Geotechnical Solutions:
Structural Solutions: Adjacent box beams; Steel pile caps, Grouted key closure joints; Asphalt overlay w/o membrane


2007 – Sauvie Island Bridge

State: OR
Year: 2007
Owner: Multnomah County
Location: Rural
Beam material: Steel

Spans: > Three-span
Max Span Length (ft.): 365
Total Bridge Length (ft.): 1177
Impact Category: Tier 1 (within 1 day)
Construction Equipment Category: SPMTs

Project Planning: State process, Design-bid-build, Contractor option
Geotechnical Solutions:
Structural Solutions: Arch span w/o deck,


2006 – Depot Street Bridge

State: OR
Year: 2006
Owner: State
Location: Urban
Beam material: Concrete

Spans: Two-span
Max Span Length (ft.): 306
Total Bridge Length (ft.): 410
Impact Category: Tier 3 (within 2 weeks)
Construction Equipment Category: Lateral Slide

Project Planning: State process, Design-bid-build, Full lane closure
Geotechnical Solutions: CIP substructure under traffic,
Structural Solutions: Arch span w/deck,


2002 – US 26 Bridge over Mill Creek

State: OR
Year: 2002
Owner: State
Location: Rural
Beam material: Steel

Spans: > Three-span
Max Span Length (ft.): 265
Total Bridge Length (ft.): 536
Impact Category: Tier 4 (within 1 month)
Construction Equipment Category: Conventional

Project Planning: State process, design-bid-build, full lane closure
Geotechnical Solutions:
Structural Solutions: Exodermic deck, CIP reinforced concrete closure joints, asphalt overlay w/o membrane


1997 – Imnaha Bridge over Little Sheep Creek

State: OR
Year: 1997
Owner: State
Location: Rural
Beam material: Steel

Spans: One-span
Max Span Length (ft.): 110
Total Bridge Length (ft.): 110
Impact Category: Tier 6 (longer but reduced by months/years)
Construction Equipment Category: Lateral Slide

Project Planning: State process, Design-bid-build,
Geotechnical Solutions:
Structural Solutions: Steel grid (concrete filled) deck, Other superstructure system - half-width curved steel girder span with concrete-filled steel-grid deck, CIP reinforced concrete closure joints