Reset Search
2012 – OR213 Bridge over Washington Street (Jughandle)
State: OR
Year: 2012
Owner: State
Location: Urban
Beam material: Steel
Spans: One-span
Max Span Length (ft.): 130
Total Bridge Length (ft.): 130
Impact Category: Tier 3 (within 2 weeks)
Construction Equipment Category: Lateral Slide
Project Planning: State process,
Design-bid-build,
Full lane closure; Best value award
Geotechnical Solutions:
Structural Solutions: FDcBs (Full-width concrete-decked steel beam unit,
CIP reinforced concrete closure joints
2012 – Burnt River & UPRR Bridge
State: OR
Year: 2012
Owner: State
Location: Rural
Beam material: Concrete
Spans: One-span
Max Span Length (ft.): 160
Total Bridge Length (ft.): 160
Impact Category: Tier 6 (longer but reduced by months/years)
Construction Equipment Category: Conventional
Project Planning: State process,
Design-bid-build,
Full lane closure
Geotechnical Solutions:
Structural Solutions: Full-depth precast deck panel w/o PT; MSE walls,
CIP reinforced concrete closure joints; Grouted blockout w/shear connectors; UHPC closure joints
2011 – Volmer and Johnson Creek Bridges
State: OR
Year: 2011
Owner: State
Location: Rural
Beam material: Concrete
Spans: One-span
Max Span Length (ft.): 29
Total Bridge Length (ft.): 29
Impact Category: Tier 4 (within 1 month)
Construction Equipment Category: Conventional
Project Planning: State process,
Design-bid-build,
Geotechnical Solutions:
Structural Solutions: adjacent slab beam; precast abutment cap w/backwall; steel sheet piling,
grouted key closure joint; socket connection (in precast substructure); epoxy joint; asphalt overlay w/membrane; precast approach slab; precast curb; other miscellaneous prefabricated element – precast sleeper slab; other miscellaneous prefabricated element – precast shear lugs
2008 – Elk Creek Bridge (Crossing No. 3)
State: OR
Year: 2008
Owner: State
Location: Rural
Beam material: Steel
Spans: Three-span
Max Span Length (ft.): 207.5
Total Bridge Length (ft.): 320.5
Impact Category: Tier 2 (within 3 days)
Construction Equipment Category: Lateral Slide
Project Planning: State process,
early environmental clearance & permitting,
design-build,
full lane closure, incentive / disincentive clause
Geotechnical Solutions: CIP substructure under traffic,
Structural Solutions: precast wingwall,
FDcBs (full-width concrete-decked steel beam unit),
CIP reinforced closure joint, precast approach slab, other miscellaneous prefabricated element – precast sleeper slab
2008 – Kimberly Bridge
State: OR
Year: 2008
Owner: State
Location: Rural
Beam material: Concrete
Spans: One-span
Max Span Length (ft.): 42
Total Bridge Length (ft.): 42
Impact Category: Tier 3 (within 2 weeks)
Construction Equipment Category: Conventional
Project Planning: State process,
design-bid-build,
full lane closure
Geotechnical Solutions:
Structural Solutions: adjacent slab beam, precast abutment cap,
grouted key closure joint, socket connection (in precast substructure), asphalt overlay w/membrane (Spans 1 & 5 only), precast curb
2007 – OR 47 Bridge over Dairy Creek Overflow
State: OR
Year: 2007
Owner: State
Location: Rural
Beam material: Concrete
Spans: One-span
Max Span Length (ft.): 45
Total Bridge Length (ft.): 45
Impact Category: Tier 3 (within 2 weeks)
Construction Equipment Category: Conventional
Project Planning: State process,
In-house forces,
Full lane closure
Geotechnical Solutions:
Structural Solutions: Adjacent box beams; Steel pile caps,
Grouted key closure joints; Asphalt overlay w/o membrane
2007 – Sauvie Island Bridge
State: OR
Year: 2007
Owner: Multnomah County
Location: Rural
Beam material: Steel
Spans: > Three-span
Max Span Length (ft.): 365
Total Bridge Length (ft.): 1177
Impact Category: Tier 1 (within 1 day)
Construction Equipment Category: SPMTs
Project Planning: State process,
Design-bid-build,
Contractor option
Geotechnical Solutions:
Structural Solutions: Arch span w/o deck,
2006 – Depot Street Bridge
State: OR
Year: 2006
Owner: State
Location: Urban
Beam material: Concrete
Spans: Two-span
Max Span Length (ft.): 306
Total Bridge Length (ft.): 410
Impact Category: Tier 3 (within 2 weeks)
Construction Equipment Category: Lateral Slide
Project Planning: State process,
Design-bid-build,
Full lane closure
Geotechnical Solutions: CIP substructure under traffic,
Structural Solutions: Arch span w/deck,
2002 – US 26 Bridge over Mill Creek
State: OR
Year: 2002
Owner: State
Location: Rural
Beam material: Steel
Spans: > Three-span
Max Span Length (ft.): 265
Total Bridge Length (ft.): 536
Impact Category: Tier 4 (within 1 month)
Construction Equipment Category: Conventional
Project Planning: State process,
design-bid-build,
full lane closure
Geotechnical Solutions:
Structural Solutions: Exodermic deck,
CIP reinforced concrete closure joints, asphalt overlay w/o membrane
1997 – Imnaha Bridge over Little Sheep Creek
State: OR
Year: 1997
Owner: State
Location: Rural
Beam material: Steel
Spans: One-span
Max Span Length (ft.): 110
Total Bridge Length (ft.): 110
Impact Category: Tier 6 (longer but reduced by months/years)
Construction Equipment Category: Lateral Slide
Project Planning: State process,
Design-bid-build,
Geotechnical Solutions:
Structural Solutions: Steel grid (concrete filled) deck,
Other superstructure system - half-width curved steel girder span with concrete-filled steel-grid deck,
CIP reinforced concrete closure joints