*Note: For keyword searches, use Keywords for Database Search with quotes (example: “Full-Depth Precast Deck Panel w/o PT”).
Reset Search
Found 5 Results

2013 – I-84 Bridges over Dingle Ridge Road

State: NY
Year: 2013
Owner: State
Location: Urban
Beam material: Concrete

Spans: One-span
Max Span Length (ft.): 82
Total Bridge Length (ft.): 82
Impact Category: Tier 1 (within 1 day)
Construction Equipment Category: Lateral Slide

Project Planning: design-bid-build, incentive / disincentive clause, value engineering
Geotechnical Solutions: CIP substructure under traffic (abutment drilled shafts constructed outside footprint of bridge),
Structural Solutions: MDcBc (Type D NEXT beams), precast wingwall, FDcBc (Full-width concrete-Decked concrete Beam unit - Type D NEXT beams), precast diaphragm, precast approach slab, other miscellaneous prefabricated element – precast sleeper slab, UHPC closure joint, asphalt overlay w/membrane


2011 – Lake Champlain Bridge

State: NY
Year: 2011
Owner: State
Location: Urban
Beam material: Steel

Spans: > Three-span
Max Span Length (ft.): 480
Total Bridge Length (ft.): 2200
Impact Category: Tier 6 (longer but reduced by months/years)
Construction Equipment Category: Other ABC Method

Project Planning: early environmental clearance & permitting; electronic shop drawing submittal & approval process, Design-Bid-Build,
Geotechnical Solutions: micropiles,
Structural Solutions: arch span w/o deck; full-depth precast deck panel w/PT; precast caisson caps, prefabricated railing


2010 – Willis Avenue Bridge over Harlem River

State: NY
Year: 2010
Owner: New York City
Location: Urban
Beam material: Steel

Spans: > Three-span
Max Span Length (ft.): 350
Total Bridge Length (ft.): 2012
Impact Category: Tier 1 (within 1 day)
Construction Equipment Category: SPMTs

Project Planning: State process; FHWA process, Right-of-way acquisition, Design-Bid-Build, Formalized partnering; Value Engineering
Geotechnical Solutions: Micropiles,
Structural Solutions: Steel grid (concrete filled) deck; Precast cap shells; Steel sheet piling; Precast retaining walls; Modular block walls; MSE walls, Truss span w/deck, CIP reinforced concrete closure joints; Grouted key closure joints; Match cast closure joints; Steel diaphragms; LWC deck


2009 – Route 31 Bridge over Canandaigua Outlet

State: NY
Year: 2009
Owner: State
Location: Rural
Beam material: Concrete

Spans: One-span
Max Span Length (ft.): 87.42
Total Bridge Length (ft.): 87.42
Impact Category: Tier 5 (within 3 months)
Construction Equipment Category: Conventional

Project Planning: Design-bid-build,
Geotechnical Solutions:
Structural Solutions: Adjacent deck bulb T beams, CIP reinforced closure joints, UHPC closure joints, asphalt overlay w/membrane


Route 23 Bridge over Otego Creek

State: NY
Year: 2009
Owner: State
Location: Rural
Beam material: Steel

Spans: One-span
Max Span Length (ft.): 131.2
Total Bridge Length (ft.): 131.2
Impact Category: Tier 5 (within 3 months)
Construction Equipment Category: Conventional

Project Planning: Design-bid-build,
Geotechnical Solutions:
Structural Solutions: Full-depth precast deck panel w/o PT (with UHPC closure joints), CIP reinforced closure joints, UHPC closure joints, standard concrete overlay