2013 – I-84 Bridges over Dingle Ridge Road
State: NY
Year: 2013
Owner: State
Location: Urban
Beam material: Concrete
Spans: One-span
Max Span Length (ft.): 82
Total Bridge Length (ft.): 82
Impact Category: Tier 1 (within 1 day)
Construction Equipment Category: Lateral Slide
Project Planning: design-bid-build,
incentive / disincentive clause, value engineering
Geotechnical Solutions: CIP substructure under traffic (abutment drilled shafts constructed outside footprint of bridge),
Structural Solutions: MDcBc (Type D NEXT beams), precast wingwall,
FDcBc (Full-width concrete-Decked concrete Beam unit - Type D NEXT beams),
precast diaphragm, precast approach slab, other miscellaneous prefabricated element – precast sleeper slab, UHPC closure joint, asphalt overlay w/membrane
2011 – Lake Champlain Bridge
State: NY
Year: 2011
Owner: State
Location: Urban
Beam material: Steel
Spans: > Three-span
Max Span Length (ft.): 480
Total Bridge Length (ft.): 2200
Impact Category: Tier 6 (longer but reduced by months/years)
Construction Equipment Category: Other ABC Method
Project Planning: early environmental clearance & permitting; electronic shop drawing submittal & approval process,
Design-Bid-Build,
Geotechnical Solutions: micropiles,
Structural Solutions: arch span w/o deck; full-depth precast deck panel w/PT; precast caisson caps,
prefabricated railing
2010 – Willis Avenue Bridge over Harlem River
State: NY
Year: 2010
Owner: New York City
Location: Urban
Beam material: Steel
Spans: > Three-span
Max Span Length (ft.): 350
Total Bridge Length (ft.): 2012
Impact Category: Tier 1 (within 1 day)
Construction Equipment Category: SPMTs
Project Planning: State process; FHWA process,
Right-of-way acquisition,
Design-Bid-Build,
Formalized partnering; Value Engineering
Geotechnical Solutions: Micropiles,
Structural Solutions: Steel grid (concrete filled) deck; Precast cap shells; Steel sheet piling; Precast retaining walls; Modular block walls; MSE walls,
Truss span w/deck,
CIP reinforced concrete closure joints; Grouted key closure joints; Match cast closure joints; Steel diaphragms; LWC deck
2009 – Route 31 Bridge over Canandaigua Outlet
State: NY
Year: 2009
Owner: State
Location: Rural
Beam material: Concrete
Spans: One-span
Max Span Length (ft.): 87.42
Total Bridge Length (ft.): 87.42
Impact Category: Tier 5 (within 3 months)
Construction Equipment Category: Conventional
Project Planning: Design-bid-build,
Geotechnical Solutions:
Structural Solutions: Adjacent deck bulb T beams,
CIP reinforced closure joints, UHPC closure joints, asphalt overlay w/membrane
Route 23 Bridge over Otego Creek
State: NY
Year: 2009
Owner: State
Location: Rural
Beam material: Steel
Spans: One-span
Max Span Length (ft.): 131.2
Total Bridge Length (ft.): 131.2
Impact Category: Tier 5 (within 3 months)
Construction Equipment Category: Conventional
Project Planning: Design-bid-build,
Geotechnical Solutions:
Structural Solutions: Full-depth precast deck panel w/o PT (with UHPC closure joints),
CIP reinforced closure joints, UHPC closure joints, standard concrete overlay