2010 – I-93 Bridge over Loudon Road (Route 9)

State: NH
Year: 2010
Owner: State
Location: Urban
Beam material: Steel

Spans: One-span
Max Span Length (ft.): 82
Total Bridge Length (ft.): 82
Impact Category: Tier 2 (within 3 days)
Construction Equipment Category: Conventional

Project Planning: State process, design-bid-build, incentive / disincentive clause, no excuse bonus, value engineering
Geotechnical Solutions:
Structural Solutions: full-depth precast deck panel w/PT, CIP reinforced closure joint, grouted key closure joint, PT ducts/bonded, asphalt overlay w/membrane


2004 – Mill Street Bridge

State: NH
Year: 2004
Owner: Town of Epping, NH
Location: Rural
Beam material: Concrete

Spans: One-span
Max Span Length (ft.): 115
Total Bridge Length (ft.): 115
Impact Category: Tier 3 (within 2 weeks)
Construction Equipment Category: Conventional

Project Planning: design-bid-build, full lane closure, incentive / disincentive clause
Geotechnical Solutions:
Structural Solutions: adjacent box beam, precast backwall, precast wingwall, precast abutment footing, grouted key closure joint, bars in splice coupler, PT ducts/bonded, asphalt overlay w/membrane