2010 – I-93 Bridge over Loudon Road (Route 9)
State: NH
Year: 2010
Owner: State
Location: Urban
Beam material: Steel
Spans: One-span
Max Span Length (ft.): 82
Total Bridge Length (ft.): 82
Impact Category: Tier 2 (within 3 days)
Construction Equipment Category: Conventional
Project Planning: State Process,
Design-bid-build,
Incentive / disincentive clauses; No Excuse bonus; Value Engineering
Geotechnical Solutions:
Structural Solutions: Full-depth precast deck panel w/PT,
CIP reinforced concrete closure joints; Grouted key closure joints; PT ducts/bonded; Asphalt overlay w/membrane
2004 – Mill Street Bridge
State: NH
Year: 2004
Owner: Town of Epping, NH
Location: Rural
Beam material: Concrete
Spans: One-span
Max Span Length (ft.): 115
Total Bridge Length (ft.): 115
Impact Category: Tier 3 (within 2 weeks)
Construction Equipment Category: Conventional
Project Planning: Design-bid-build,
Full lane closure; Incentive / disincentive clauses
Geotechnical Solutions:
Structural Solutions: Adjacent box beams; Precast backwalls; Precast wingwalls; Precast abutment footings,
Grouted key closure joint; Bars in splice couplers; PT ducts/bonded; Asphalt overlay w/membrane