2010 – Biltmore Avenue Bridge
State: NC
Year: 2010
Owner: State
Location: Urban
Beam material: Steel
Spans: One-span
Max Span Length (ft.): 135
Total Bridge Length (ft.): 135
Impact Category: Tier 6 (longer but reduced by months/years)
Construction Equipment Category: Conventional
Project Planning: • Design-Bid-Build,
• Full lane closure
Geotechnical Solutions: • Micropiles,
Structural Solutions: MDcBs (Modular decked beams),
CIP reinforced concrete closure joints

2010 – US 17 Bridge over Tar River (Washington Bypass)
State: NC
Year: 2010
Owner: State
Location: Rural
Beam material: Concrete
Spans: > Three-span
Max Span Length (ft.): 121.67
Total Bridge Length (ft.): 14784
Impact Category: Tier 6 (longer but reduced by months/years)
Construction Equipment Category: Other ABC Method
Project Planning: design-build,
full lane closure, incentive / disincentive clause, formalized partnering
Geotechnical Solutions:
Structural Solutions: precast pile cap,
PT ducts/bonded, socket connection (in precast substructure)

2008 – NC 12 Bridge over Molasses Creek
State: NC
Year: 2008
Owner: State
Location: Urban
Beam material: Concrete
Spans: > Three-span
Max Span Length (ft.): 51
Total Bridge Length (ft.): 252
Impact Category: Tier 5 (within 3 months)
Construction Equipment Category: Conventional
Project Planning: design-bid-build,
full lane closure, incentive / disincentive clause, lump sum bonus, contractor revision
Geotechnical Solutions:
Structural Solutions: adjacent slab beam, precast pile cap, precast abutment cap, precast backwall, precast wingwall, precast abutment footing,
grouted key closure joint, PT ducts/un-bonded, socket connection (in precast caps), grouted duct connection (in precast backwalls), asphalt overlay w/o membrane, prefabricated railing

1999 – Beaufort and Morehead Railroad Trestle Bridge
State: NC
Year: 1999
Owner: State
Location: Urban
Beam material: Concrete
Spans: > Three-span
Max Span Length (ft.): 33
Total Bridge Length (ft.): 495
Impact Category: Tier 3 (within 2 weeks)
Construction Equipment Category: Conventional
Project Planning: design-build,
full lane closure (i.e., full track closure)
Geotechnical Solutions:
Structural Solutions: adjacent T beam, precast pile cap, precast abutment cap, precast backwall, precast wingwall,
pocket connection (in precast substructure), prefabricated railing, other miscellaneous prefabricated element – precast flat slab transition span and thrust block rib

1983 – Linn Cove Viaduct
State: NC
Year: 1983
Owner: National Park Service
Location: Rural
Beam material: Concrete
Spans: > Three-span
Max Span Length (ft.): 180
Total Bridge Length (ft.): 1243
Impact Category: Tier 6 (longer but reduced by months/years)
Construction Equipment Category: Other ABC Method
Project Planning: FHWA Process,
Design-Bid-Build,
Geotechnical Solutions: Micropiles,
Structural Solutions: Precast segmental beam elements; Precast column(s),
PT ducts/bonded