2013 – Milton-Madison Bridge

State: IN
Year: 2013
Owner: States (Indiana and Kentucky)
Location: Urban
Beam material: Steel

Spans: > Three-span
Max Span Length (ft.): 727
Total Bridge Length (ft.): 3200
Impact Category: Tier 3 (within 2 weeks)
Construction Equipment Category: Lateral Slide

Project Planning: design-build, full lane closure
Geotechnical Solutions: reused substructure/foundation unit, high-capacity pile, other foundation/wall: finite element analysis of existing pier caissons with passive soil resistance / scour mitigation,
Structural Solutions: MSE wall, truss span w/deck, CIP reinforced closure joint


1999 – Sedley Bridge

State: IN
Year: 1999
Owner: County
Location: Rural
Beam material: Concrete

Spans: One-span
Max Span Length (ft.): 110.5
Total Bridge Length (ft.): 110.5
Impact Category: Tier 6 (longer but reduced by months/years)
Construction Equipment Category: Conventional

Project Planning: design-bid-build, full lane closure
Geotechnical Solutions:
Structural Solutions: PT concrete through-girder, full-depth precast deck panel w/PT, MSE wall, grouted key closure joint, PT ducts/bonded, micro-silica concrete overlay