2020 – Clark Fork River Bridge

Year ABC Built: 2020
State: MT
County: Sanders
Owner: State
Location: Rural
Spans: > Three-span
Beam material: Steel
Max Span Length (ft.): 200
Total Bridge Length (ft.): 920
Construction Equipment Category: Other ABC Method
ABC Construction Equipment: high-capacity crane(s), other ABC equipment - Small hydraulic/rail buggy transport for panel placement. Reduced loads on structure, expedited panel placement times, reducing road closure time. Also, access was obtained below the entire superstructure using a lightweight hanging construction platform (safe span).
State ID Number: 05271
NBI Number: P00006028+01091
Coordinates
Latitude:
47.85254 | Longitude: -115.61083
{"autoplay":"true","autoplay_speed":"4000","speed":"300","arrows":"true","dots":"true","rtl":"false"}

Under Construction


Bridge Description

Project Summary:

This project was MDT’s first use of CM/GC. The deck replacement consisted of full-width, full-depth precast deck panels and specialized conventional concrete closure joints.


Project Location:

on Montana Hwy 200 over Clark Fork River at head of Noxon Reservoir near small community of Trout Creek in northwest corner of Montana


Impact Category:

Tier 5 (within 3 months)


Mobility Impact Time:
  • ABC: 6 weeks
  • Conventional: 12 weeks


Primary Drivers:
  • reduced traffic impacts
  • reduced onsite construction time
  • improved work-zone safety
  • improved site constructability
  • minimized environmental impacts
  • minimize business impacts
  • maintain essential services


Dimensions:

Main spans: 920-ft-long and 34.33-ft-wide 5-span steel-girder bridge (160 ft – 200 ft – 200 ft- 200 ft – 160 ft); no skew


Average Daily Traffic (at time of construction):

1960


Traffic Management (if constructed conventionally):

extended use of a 23-mile detour for local traffic and a larger multi-state alternative route for through-traffic


Existing Bridge Description:

The existing 2-girder non-redundant 7-span bridge was 1,051-ft long (with approach spans included) and 28-ft wide with two traffic lanes. It was originally constructed over the Noxon Reservoir in 1958 prior to the filling of the reservoir. The deck was in poor condition with significant delamination and high chloride concentration from the frequent use of anti-icing chemicals.


Replacement or New Bridge:

The new 920-ft-long (main spans) deck replacement has a 32-ft-wide roadway with two 11-ft-wide traffic lanes and two 5-ft-wide shoulders. The cross-section consists of 9.5-ft-long, 34.33-ft-wide (full-width), 6.5-inch-thick precast deck panels with specialized conventional concrete joint connections.


Construction Method:

The existing bridge’s limited roadway width and two-girder system posed safety concerns that made phased construction impractical. The MDT determined that the bridge will have several more decades of functional life with a new deck and rehabilitated superstructure/substructure.

 

The deck panels were prefabricated locally in Kalispell, Montana, approximately 125 miles from the project site. Ninety-eight (98) full-width deck panels, each 34.33-ft wide and 9.5-ft long, weighing approximately 25,000 lbs, were required for the project. Each panel was fabricated with blockout sections for shear studs, leveling devices, and haunch concrete. A formless joint system was used between adjacent panels to ensure proper transverse connection. The panels were cast with MMFX reinforcement, and with epoxy-coated steel reinforcement protruding at the outside edges for traffic railing connections. The contractor built a mockup at the prefabrication plant to ensure proper fit-up and placement of joint concrete.

 

Concurrent with panel prefabrication and prior to bridge closure, temporary scaffolding was installed beneath the bridge to provide safe access for the rehabilitation work and for containment of construction debris.

 

The bridge was closed in June 2025 for 6 weeks, the maximum closure time allowed in the contract. During this time, the existing deck was carefully removed to avoid damaging the steel girders. Bearings were upgraded, as well as some beam seat improvements to the concrete substructure. The steel superstructure was cleaned and spot painted as deemed appropriate.

 

Two cranes were used to place the deck panels. Each panel was picked up by one crane and placed on a delivery cart that carried the panel to the second crane. The second crane, on a tresle, placed the deck panels in sequence. Blockouts and transverse formless joints were cast with specialized conventional concrete, as the use of Ultra-High Performance Concrete was avoided due to regional shortages in steel fibers and cost considerations. Rehabilitation work was also done on the approach spans at each end of the bridge.

 

Once the deck was in place, the cast-in-place concrete railing was constructed, and a 1.5-inch standard concrete overlay was applied.

 

The project included an incentive/disincentive clause of $9,000 per day, with a maximum incentive of $90,000.


Stakeholder Feedback:
  • Creating a mock-up of the deck panels was essential for identifying and resolving potential issues before full-scale fabrication.
  • The Construction Manager/General Contractor (CM/GC) approach was highly effective for this project. It enabled early collaboration among MDT, engineers, and the contractor, allowing potential risks and design issues to be addressed upfront, which proved beneficial for the project’s success.
  • The use of smaller shear studs, where feasible, could simplify deck panel construction and joint connections. The large 1.25-inch studs caused challenges.
  • The construction phase coincided with the COVID-19 pandemic, causing significant supply chain disruptions.
  • The project had only 8 months from the kickoff to the contract award, which compressed planning and design, adding pressure on all parties to meet deadlines.

High Performance Material:

MMFX corrosion-resistant steel in panels



Project Planning

Decision Making Tools: State process, benefit/cost method
Site Procurement:
Project Delivery: CM/GC
Contracting: full lane closure, incentive / disincentive clause

Geotechnical Solutions

Foundations & Walls: reused substructure/foundation unit
Rapid Embankment:

Structural Solutions

Prefabricated Bridge Elements: full-depth precast deck panel w/o PT
Prefabricated Bridge Systems: other superstructure / substructure system - seismic retrofits improving seat length and bearings at abutments
Miscellaneous Prefabricated: CIP reinforced closure joint, standard concrete overlay

Costs & Funding

Costs:

The awarded bid was $10.5 million. The cost for the deck panels was $3.5 million. The cost of driving surface was $412.31/sq ft for the entire project. The cost of precast deck panels was $112/sq ft.


Funding Source:

Federal and State


Incentive Program:

Additional Information

October 2021 ABC-UTC Monthly Webinar, “Montana’s ABC Clark Fork River Bridge Rehabilitation near Trout Creek”


Downloadable Resources

Contract Plans:

View MT_Clark_Fork_Plans.pdf

Specifications:

View MT_Clark_Fork_Special_Provisions.pdf

Bid Tabs:

View MT_Clark_Fork_Bid_Tabs.pdf

Construction Schedule:


Other Related Information:


Other Related URLs:


Photo Credits:

Montana Department of Transportation


Contacts

Owner:
Andy Cullison, P.E.
State Bridge Engineer
Montana Department of Transportation (MDT)
Email: acullison@mt.gov
Phone: 406-444-6260

Designer:
HDR

Contractor:
Kiewit

Precaster:
Glacier Precast

Submitter:
IBT/ABC-UTC Graduate Student Submissions Initiative
Adeyemi Sowemimo, Ph.D. Candidate
Research Assistant
University of Georgia