State: PA
County: Allegheny
Owner: State
Location: Urban
Spans: Two-span
Beam material: Steel
Max Span Length (ft.): 70
Total Bridge Length (ft.): 140
Construction Equipment Category: SPMTs
ABC Construction Equipment: SPMTs
State ID Number: BMS # 02/3110/0010/0001
NBI Number: 54732 - BRKEY
Coordinates
Latitude: 40.433333 | Longitude: -80.028889
Bridge Description
Project Summary:This project was the first time that Self-Propelled Modular Transporters (SPMTs) were used by PennDOT to replace a bridge, and was considered a pilot project.
Project Location:
Shaler Street over SR 19 (Saw Mill Run Blvd) near the city of Pittsburgh in southwest Pennsylvania
Impact Category:
Tier 5 (within 3 months)
Mobility Impact Time:
- ABC: 71-day closure of Shaler Street; two weekend closures of SR 19
- Conventional: approximately 6-month closure
Primary Drivers:
- Reduced traffic impacts
- Reduced onsite construction time
- Improved work-zone safety
- Improved site constructability
- Single construction season
- Maintain existing alignment
- Minimize business impacts
- Maintain essential services
- Other primary driver – availability of federal grant to rent the SPMTs and try out this innovative ABC technology
Dimensions:
34.42-ft wide, 140-ft long two-span (70 ft – 70 ft) steel plate girder bridge, 5° skew, 14% profile grade
Average Daily Traffic (at time of construction):
27000
Traffic Management:
There would have been an additional 4-month closure of Shaler St if ABC was not used.
Existing Bridge Description:
Built in 1949, the existing structure was a 162-ft-long, three-span (60 ft - 56 ft - 42 ft) bridge with a 24-ft-wide roadway and two 6-ft-wide sidewalks. It climbed at a rate of 14% grade over SR 19.
Replacement or New Bridge:
The new bridge is a 140-ft-long, two-span (70 ft each) continuous-for-live-load steel plate girder bridge. It is 34.42-ft wide with a 26-ft roadway and one 5.67-ft sidewalk. The superstructure cross-section consists of five Grade 50 steel plate girders with a reinforced concrete deck. The substructure consists of cast-in-place concrete abutments and interior pier founded on drilled caissons.
Construction Method:
During preliminary design, PennDOT had multiple discussions with heavy move contractors to explain the scope of the project and complications of the project site to confirm that an SPMT bridge move was feasible. They developed a 3D finite element model to analyze dynamic effects during the move and determined tolerances. They evaluated the move path for horizontal clearances and grade changes.
With this project being their first SPMT bridge move, PennDOT wanted to make sure their intent for the project was clear to the contractors who would be bidding on the project and to the construction inspection staff. They decided to provide conceptual construction sequence plans and conceptual plans for the bridge move path and bridge staging area, with the intent that the contractor could have flexibility to do what worked best for them. They also developed an animation to show how they envisioned the bridge construction and move; this was also shared with the media and general public.
The two new spans were built at the final 14% grade on temporary supports in an adjacent staging area approximately 500 ft from the bridge site. Abutment #2, the uphill abutment, was constructed under the existing bridge prior to bridge closure. Only portions of Abutment #1 could be constructed prior to bridge closure due to site constraints.
The existing bridge was closed and demolished during the first weekend closure of SR 19 (September 6-8, 2019). The contractor changed the precast cheek walls and precast interior pier to conventional cast-in-place concrete construction. The abutments and pier were completed after the bridge was demolished. During the second weekend closure of SR 19 (November 3-5, 2019), the coarse-aggregate move path with maximum 4% grade was constructed. The two new spans (each weighing approx. 260 tons) were moved individually from the staging area into their final positions using a single set of SPMTs. The temporary grading was removed prior to opening SR 19. A continuity connection was provided over the pier to make the spans continuous for live load. Shaler Street was closed for a total of 71 days (September 6 – November 22, 2019).
The special provisions for the project required that SPMTs be used for installing the new superstructure; this was also discussed at a pre-bid meeting for the project. In addition, PennDOT provided extensive public outreach coordination throughout the project.
Stakeholder Feedback:
Lessons Learned:
- Require submission of a stakeout plan for the new superstructure in its temporary location.
- Maintain contact between jacking falsework and the superstructure until final position is achieved.
- Oversize the anchor bolt hole locations, or set the bridge and then drill the anchor bolt locations.
- Require move path elevations on the move plan.
- Have a contingency plan for equipment malfunctions.
- Require SPMT move submissions early in the construction process to help identify any potential issues or conflicts that could delay the project.
- Pay close attention to the horizontal dimensions of the move path (clearances and width of road) to avoid interference with power lines, formwork, buildings, trees, rockfall fence, etc.
- The temporary grading needs to be wide enough to allow the SPMTs to have flexibility to move transversely. Placing plywood along the shoulder of the path can prevent the grading from sloughing where the SPMT wheels get close to the grading edge, but can be time consuming to place and move.
- Make temporary diaphragms, added between the beams for the SPMT pick points, permanent to avoid time delay otherwise required for removal.
- The temporary bumpers, intended to prevent downhill movement of the spans prior to anchor bolt installation because of the 14% grade, were difficult to work around while setting the spans. These temporary bumpers proved to be unnecessary because the bearings were made level with beveled sole plates.
High Performance Material:
none
Project Planning
Decision Making Tools: FHWA process, state processSite Procurement: right-of-way acquisition
Project Delivery: design-bid-build
Contracting: full lane closure
Geotechnical Solutions
Foundations & Walls: high-capacity pile, CIP substructure under traffic, other foundation/wall - soil nail wallRapid Embankment:
Structural Solutions
Prefabricated Bridge Elements: precast cheek wall, precast lagging panel, other abutment and wall element - soldier pile and lagging wingwallPrefabricated Bridge Systems: FDcBs
Miscellaneous Prefabricated: steel diaphragm, CIP reinforced closure joint, other closure joint/connection - simple for dead load, continuous for live load connection at pier
Costs & Funding
Costs:Five prime contractors bid on the project. Awarded low bid: $3.66 Million (Swank). Total cost with ABC was $3.7M, compared to an estimated $2.9M for conventional construction. The SPMT-related items cost about $750,000. User-cost savings were estimated at $2.2M.
Funding Source:
Federal and State
Incentive Program:
$400,000 IBRD [Innovative Bridge Research and Deployment] grant from Federal Highway Administration to rent the SPMTs and try out this innovative ABC technology.
Additional Information
ABC-UTC April 2020 Webinar, “PennDOT’s First SPMT Bridge Move: Shaler Street Bridge”
Downloadable Resources
Contract Plans:
View PA-2019-ShalerSt_BridgePlans.pdf
View PA-2019-ShalerSt_Pub-408-Section-704.pdf
View PA-2019-ShalerSt_Pub-408-Section-1001.pdf
Construction Schedule:
Other Related Information:
PennDOT; H. W. Lochner, Inc.
Contacts
Owner:
Keith Cornelius, P.E.
District Bridge Engineer, District 11-0
PennDOT
Email: kcornelius@pa.gov
Phone: 412-429-2855
Former PennDOT District 11-0 Bridge Engineer at the time of the project:
Lou Ruzzi, P.E.
WSP USA Inc.
Email: louis.ruzzi@wsp.com, or: lruzzi@comcat.net
Designer:
Matthew E. Cochran, P.E.
Senior Structural Engineer (Design)
H. W. Lochner, Inc.
Email: mcochran@hwlochner.com
Contractor:
Cary Basinger, P.E.
Project Manager
Swank Construction Company, LLC
Heavy Move Contractor:
Mammoet


