TH 36 over Keller Lake Bridge

  • Year ABC Built: 2013
  • State: Minnesota
  • Owner: State
  • Location: Urban
  • Spans: Three-span
  • Beam Material: Concrete
  • Max Span Length (ft.): 46.50
  • Total Bridge Length (ft.): 118.10
  • Construction Equipment: Conventional
  • State ID #: 62037
  • NBI #: 000000000062037
  • Coordinates:     Latitude: 45.0114784, Longitude: -93.0628128
  • Bridge Description

  • Project Summary: superstructure and substructure precast elements
  • Project Location: On State Highway 36 from Arcade Street to State Highway 61 southbound exit ramp in the city of Maplewood in Ramsey County
  • Mobility Impact Time: 65 calendar days for ABC vs. 75 calendar days for conventional construction
  • Impact Category: Tier 5 (within 3 months)
  • Primary Drivers:

    reduced onsite construction time; improved site constructability; improved material quality and product durability; minimized environmental impacts

  • Dimensions: 118.1-ft-long and 89.8-ft-wide 3-span prestressed inverted tee bridge (34.75 ft – 46.5 ft – 34.75 ft); 0º skew
  • Average Daily Traffic (at time of construction): 69000
  • Traffic Management:
  • Existing Bridge Description: The existing 3-span concrete tee beam bridge was 112.5-ft long and 80-ft wide with integral abutments. It had four 12 ft-wide traffic lanes and 2 ft inside and 10 ft outside shoulders. Built in 1937, the bridge was deteriorated and required replacement. 
  • Replacement or New Bridge: The replacement bridge has four 12-ft-wide traffic lanes, 2 ft inside and 10 ft outside shoulders. The cross-section consists of sixteen 1.5-ft-deep inverted tee beams spaced at 5.83 feet with a 7-inch-thick cast-in-place reinforced concrete deck. The precast concrete integral abutments were founded on prestressed concrete piling (prestressed concrete piling is new to MnDOT).  In addition to the inverted tees, other prefabricated elements included precast concrete pier caps and precast concrete abutment components.
  • Construction Method: The beams with their maximum 6-ft overall width allowed standard hauling and quick erection. This project was completed using staged construction.  In each of the stages the contractor drove the prestressed concrete piles for the abutments and piers. A typical crane for this scale of project was used to install the precast abutments, pier caps and inverted tee beams. The precast abutment pieces and precast caps were connected to the piles using high-strength flowable grout. The precast inverted tee beams were erected, the longitudinal “drop in” steel reinforcement and deck reinforcement were placed, and the deck was cast and cured. For the first stage deck placement a conventional deck mix was used.  For the second stage the deck mix was modified to use polypropylene fibers to reduce cracking.The contract required bridge construction to be completed in 60 calendar days.  Liquidated damages were $10,000 per day over 60 days.
  • Stakeholder Feedback:

    An inspection was conducted one year after the bridge was opened to traffic. Map cracking was detected on the deck surface of the stage that used the conventional deck mix.  The second stage placement that included polypropylene fibers exhibited significantly less cracking.  Future deck placements of this superstructure type will require fibers in the deck mix.

  • High Performance Material: polypropylene fibers in concrete deck
  • Project Planning

  • Decision Making Tools: (none)
  • Site Procurement: (none)
  • Project Delivery: design-bid-build
  • Contracting: incentive / disincentive clause
  • Geotechnical Solutions

  • Foundations & Walls: (none)
  • Rapid Embankment: (none)
  • Structural Solutions

  • Prefabricated Bridge Elements: precast pile caps; precast abutment stems; precast wingwalls; adjacent inverted T beams
  • Prefabricated Bridge Systems: (none)
  • Miscellaneous Prefabricated: socket connection (in precast substructure)
  • ABC Construction Equipment: conventional
  • Cost & Funding

  • Costs: The engineer’s estimate for the project was $ 2,386,566. The low bid was $2,073,956. There were 3 bidders. The cost per square foot of bridge was $195.66 compared to $155.58 for conventional construction in this region during the same time period.
  • Funding Source: (none)
  • Incentive Program: (none)
  • Additional Information

Downloadable Resources

Contract Plans:
Specifications:
Bid Tabs:
Other Related Information:
Photo Credits: Minnesota Department of Transportation

 

Contacts

Owner: Paul Rowekamp, P.E.
Bridge Standards and Research Engineer
Minnesota Department of Transportation
paul.rowekamp@state.mn.us
651-366-4484

Designer: Angel Staples, P.E.
MNDOT/Bridge Office
angel.staples@state.mn.us
651-366-4546

Contractor: Jerry Volz
Ames Construction
JerryVolz@amesco.com
952-435-7106

Submitter: Paul Rowekamp, P.E.
Bridge Standards and Research Engineer
Minnesota Department of Transportation
paul.rowekamp@state.mn.us
651-366-4484